DIGGIN' DOWNTOWN UPDATE - 3/7

Last Updated 9/26/2025Posted in DIGGIN' DOWNTOWN

Date: March 7, 2025

Recent Weeks:

Water Main Installation

Pavement Removal

Next Week:

Phase 1A Washington Street

Monday 3/10 – Contractor will begin installing water services along Washington Street on the west side of Fillmore Street.

Tuesday 3/11 – Contractor will complete installation of water services along Washington Street on the west side of Filmore Street. Contractor to begin sidewalk removals in front of fire station to complete fire station water service installation.

Wednesday 3/12 to Friday 3/14 – Contractor to begin sidewalk removals and water service installations in front of businesses on north side of Washington Street.

*Please Note –Sections of sidewalk will be temporarily inaccessible during water service installation.

Looking Ahead:

Washington Street will remain closed as utility installation continues through the following weeks.

Follow along here to see the latest progress!

Project Facebook Page:

https://www.facebook.com/DowntownOsceolaStreetscapeProject/


Diggin Downtown Update - 10/17Date: October 17, 2025 Recent Weeks: Underground Utility Service installation (Main St/Jefferson St) Curb and Gutter installation (Main ...
Halloween Happenings: Frights, Fun, and Festivities Await! Spooky season is creeping in… and Osceola is brewing up a fang-tastic lineup of Halloween fun for all ages! From family trick-or-treatin...
Diggin Downtown Update - 10/10Date: October 10, 2025 Recent Weeks: Underground Utility Service Installation (East Jefferson St) Lighting System Installation (Washingt...
A New Chapter Begins at The Velvet Nook & RoastDowntown Osceola is turning the page on something truly special! On Tuesday, September 30, we gathered to celebrate the ribbon cutting a...