DIGGIN' DOWNTOWN UPDATE - 4/4

Last Updated 9/26/2025Posted in DIGGIN' DOWNTOWN

Date: April 4, 2025

Recent Weeks:

Sanitary Sewer Installation

Manhole Installation

Pavement Removal

Next Week:

Phase 1A Washington Street

Monday 4/7 to Tuesday 4/8 – Contractor to begin storm sewer installation along Washington Street.

Wednesday 4/9 to Friday 4/11 – Contractor will continue storm sewer installation along Washington Street, as well as begin preparation for sidewalk installation on the north side of Washington Street.

Looking Ahead:

Washington Street will remain closed as storm sewer installation continues through the following weeks.

Contractor will move to Main Street to install new water main once storm sewer installation is complete.

Follow along here to see the latest progress!

Project Facebook Page:

https://www.facebook.com/DowntownOsceolaStreetscapeProject/

Christmas in the Park Brings Holiday Magic to Downtown O... Downtown Osceola came to life on Saturday, December 6, as families, friends, and visitors gathered to celebrate one of our favorite comm...
Diggin' Downtown Update 11/26Date: November 26, 2025 Recent Weeks: Underground Utility Service Installation (West Jefferson St) Subgrade Compaction, Subbase, Subdrai...
Diggin Downtown Update 11/21Date: November 21, 2025 Recent Weeks: Underground Utility Service Installation (Jefferson St) Subgrade Compaction, Subbase, Subdrain Ins...
Shop Local This Holiday Season: Osceola Has Something fo... The holiday season is officially here, and as we inch closer to Shop Small Saturday on November 29 , our local businesses are buzzing wi...