Date: April 11, 2025
This Past Week:
Storm Sewer Installation
Sidewalk Installation
Next Week:
Phase 1A Washington Street
Monday 4/14 to Friday 4/18 – Contractor to continue storm sewer and sidewalk installations along Washington Street.
Looking Ahead:
Washington Street will remain closed as storm sewer installation continues through the following weeks.
Pavement preparation along Washington Street to begin after storm sewer installation. Contractor will move to Main Street to install new water main once storm sewer installation is complete.

Follow along here to see the latest progress!

Project Facebook Page:

https://www.facebook.com/DowntownOsceolaStreetscapeProject/

Diggin Downtown Update - 10/17Date: October 17, 2025 Recent Weeks: Underground Utility Service installation (Main St/Jefferson St) Curb and Gutter installation (Main ...
Halloween Happenings: Frights, Fun, and Festivities Await! Spooky season is creeping in… and Osceola is brewing up a fang-tastic lineup of Halloween fun for all ages! From family trick-or-treatin...
Diggin Downtown Update - 10/10Date: October 10, 2025 Recent Weeks: Underground Utility Service Installation (East Jefferson St) Lighting System Installation (Washingt...
A New Chapter Begins at The Velvet Nook & RoastDowntown Osceola is turning the page on something truly special! On Tuesday, September 30, we gathered to celebrate the ribbon cutting a...