DIGGIN' DOWNTOWN UPDATE - 6/6

Last Updated 9/26/2025Posted in DIGGIN' DOWNTOWN

Date: June 6, 2025

Recent Weeks:

Subdrain Installation (Washington St)

Concrete Paving Operations (Washington St)

Storm Sewer installation (Main Street)

Next Week:

Phase 1A Washington Street

Monday 6/9 to Friday 6/13 – Contractor to continue PCC (Plain Cement Concrete) street and sidewalk installation along Washington Street.

Phase 1B Main Street

Monday 6/9 to Friday 6/13– Contractor to continue storm sewer utility installation.

Looking Ahead:

Washington Street will remain closed as paving operations continue throughout the following weeks. Main Street will remain closed for utility installation.


Follow Downtown Osceola Streetscape Project on Facebook to follow along with the progress.

Diggin Downtown Update - 10/17Date: October 17, 2025 Recent Weeks: Underground Utility Service installation (Main St/Jefferson St) Curb and Gutter installation (Main ...
Halloween Happenings: Frights, Fun, and Festivities Await! Spooky season is creeping in… and Osceola is brewing up a fang-tastic lineup of Halloween fun for all ages! From family trick-or-treatin...
Diggin Downtown Update - 10/10Date: October 10, 2025 Recent Weeks: Underground Utility Service Installation (East Jefferson St) Lighting System Installation (Washingt...
A New Chapter Begins at The Velvet Nook & RoastDowntown Osceola is turning the page on something truly special! On Tuesday, September 30, we gathered to celebrate the ribbon cutting a...