Recent Weeks:
Concrete Paving Operations (Washington & Main St)
Underground Utility Installation (Washington Street/Main Street)


Next Week:
Phase 1A Washington Street
Monday 8/11 to Friday 8/15 – Contractor to complete subgrade preparation, subbase and subdrain installation along East Washington Street

Phase 1B Main Street
Monday 8/11 to Friday 8/15 – Contractor to continue water main installation along Main Street.

Looking Ahead:
Week of August 11 and 18: Water main installation on Main Street and paving operations on East Washington
Week of August 25: Jefferson/Main Intersection and East Jefferson closed for removals. Water services for Main Street businesses.
Diggin Downtown Update - 10/17Date: October 17, 2025 Recent Weeks: Underground Utility Service installation (Main St/Jefferson St) Curb and Gutter installation (Main ...
Halloween Happenings: Frights, Fun, and Festivities Await! Spooky season is creeping in… and Osceola is brewing up a fang-tastic lineup of Halloween fun for all ages! From family trick-or-treatin...
Diggin Downtown Update - 10/10Date: October 10, 2025 Recent Weeks: Underground Utility Service Installation (East Jefferson St) Lighting System Installation (Washingt...
A New Chapter Begins at The Velvet Nook & RoastDowntown Osceola is turning the page on something truly special! On Tuesday, September 30, we gathered to celebrate the ribbon cutting a...