DIGGIN' DOWNTOWN UPDATE - 7/18
Date: July 18, 2025
Recent Weeks:
(Washington Street/Main Street)
Storm Sewer installation
Permeable Paver Installation (Washington St)
Concrete Paving Operations (Washington St)
Next Week:
Phase 1A Washington Street
Monday 7/21 to Friday 7/25 – Contractor to continue permeable paver and subdrain installation along Washington Street.
Phase 1B Main Street
Monday 7/21 to Friday 7/25 – Sanitary Sewer installation will begin along Washington Street east of Main Street. Contractor will move to water main installation at the intersection of Washington Street and Main Street toward the end of the week.
Looking Ahead:
Washington Street will remain closed as paving and permeable paver installations continue throughout the following weeks. Main Street and East Washington Street will remain closed for utility installation.