DIGGIN DOWNTOWN UPDATE - 7/25
Date: July 25, 2025
Recent Weeks:
Concrete Paving Operations (Washington St)
Permeable Paver Installation (Washington St)
Storm Sewer installation (Washington Street/Main Street)
Water Main Installation (Washington Street/Main Street)
Next Week:
Phase 1A Washington Street
Monday 7/28 to Friday 8/1 – Contractor to continue permeable paver and sidewalk installation along Washington Street. Subgrade prep on Main/Washington Intersection.
Phase 1B Main Street
Monday 7/28 to Friday 8/1 – Contractor to continue water main and water service installation along East Washington Street.
Looking Ahead:
Washington Street will remain closed as sidewalk and permeable paver installations continue throughout the following weeks. Main Street and East Washington Street will remain closed for utility installation.