DIGGIN DOWNTOWN UPDATE - 8/8

Last Updated 8/11/2025Posted in DIGGIN' DOWNTOWN

Date: August 8, 2025 
Recent Weeks:
Concrete Paving Operations (Washington & Main St)
Underground Utility Installation (Washington Street/Main Street)


Next Week:
Phase 1A Washington Street
Monday 8/11 to Friday 8/15 – Contractor to complete subgrade preparation, subbase and subdrain installation along East Washington Street

Phase 1B Main Street
Monday 8/11 to Friday 8/15 – Contractor to continue water main installation along Main Street.

Looking Ahead:
Week of August 11 and 18: Water main installation on Main Street and paving operations on East Washington
Week of August 25: Jefferson/Main Intersection and East Jefferson closed for removals. Water services for Main Street businesses.
Osceola Chamber Main Street Lights Up Downtown with New ... Osceola Chamber Main Street has taken another bold step in transforming the heart of downtown into a vibrant, welcoming destination. The...
DIGGIN DOWNTOWN UPDATE - 8/8Date: August 8, 2025 Recent Weeks: Concrete Paving Operations (Washington & Main St) Underground Utility Installation (Washington Street...
DIGGIN DOWNTOWN UPDATE - 7/25Date: July 25, 2025 Recent Weeks: Concrete Paving Operations (Washington St) Permeable Paver Installation (Washington St) Storm Sewer in...
DIGGIN' DOWNTOWN CONSTRUCITON SCHEDULE OVERVIEWRemainder of July East Washington utility work Washington street pavers and concrete operations Subgrade prep on Main/Washington Interse...