DIGGIN DOWNTOWN UPDATE - 8/8

Last Updated 9/26/2025Posted in DIGGIN' DOWNTOWN

Date: August 8, 2025 
Recent Weeks:
Concrete Paving Operations (Washington & Main St)
Underground Utility Installation (Washington Street/Main Street)


Next Week:
Phase 1A Washington Street
Monday 8/11 to Friday 8/15 – Contractor to complete subgrade preparation, subbase and subdrain installation along East Washington Street

Phase 1B Main Street
Monday 8/11 to Friday 8/15 – Contractor to continue water main installation along Main Street.

Looking Ahead:
Week of August 11 and 18: Water main installation on Main Street and paving operations on East Washington
Week of August 25: Jefferson/Main Intersection and East Jefferson closed for removals. Water services for Main Street businesses.
Shop Local This Holiday Season: Osceola Has Something fo... The holiday season is officially here, and as we inch closer to Shop Small Saturday on November 29 , our local businesses are buzzing wi...
DIGGIN DOWNTOWN UPDATE - 11/7Date: November 7, 2025 Recent Weeks: Underground Utility Service Installation (Jefferson St) Permeable Paver installation (Main St) Side...
DIGGIN DOWNTOWN UPDATE - 10/31Date: October 31, 2025 Recent Weeks: Underground Utility Service Installation (Main St/E Jefferson St) Permeable Paver Installation (Mai...
DIGGIN DOWNTOWN UPDATE - 10/24Date: October 24, 2025 Recent Weeks: Underground Utility Service Installation (Main St/Jefferson St) Curb and Gutter installation (Main ...