DIGGIN DOWNTOWN UPDATE - 8/15

Last Updated 8/18/2025Posted in DIGGIN' DOWNTOWN

Date: August 15, 2025 

Recent Weeks:
Pavement Removals (Jefferson St & Main St)
Underground Utility Installation (Main St)

Next Week:
Phase 1A Washington Street
Monday 8/18 to Friday 8/22 – Contractor to complete subgrade preparation, subbase and subdrain installation along East Washington Street.
Phase 1B Main Street
Monday 8/18 to Friday 8/22 – Contractor to continue water main installation at Jefferson and Main Street intersection. Begin service installations along Main Street.

*Please note – Sections of sidewalk along Main Street will be inaccessible while sanitary and water service installation is underway.

Looking Ahead:
East Washington Street will remain closed as paving preparation and installation continue throughout the following weeks. Main Street and the intersection of Main Street and Jefferson Street will remain closed for utility installation.
DIGGIN DOWNTOWN UPDATE - 8/15Date: August 15, 2025 Recent Weeks: Pavement Removals (Jefferson St & Main St) Underground Utility Installation (Main St) Next Week: Pha...
Osceola Chamber Main Street Lights Up Downtown with New ... Osceola Chamber Main Street has taken another bold step in transforming the heart of downtown into a vibrant, welcoming destination. The...
DIGGIN DOWNTOWN UPDATE - 8/8Date: August 8, 2025 Recent Weeks: Concrete Paving Operations (Washington & Main St) Underground Utility Installation (Washington Street...
DIGGIN DOWNTOWN UPDATE - 7/25Date: July 25, 2025 Recent Weeks: Concrete Paving Operations (Washington St) Permeable Paver Installation (Washington St) Storm Sewer in...