DIGGIN DOWNTOWN UPDATE - 9/8

Last Updated 9/8/2025Posted in DIGGIN' DOWNTOWN

Date: September 5, 2025

Recent Weeks:

Underground Utility Service Installation (Main St)

Paving Operations (East Washington St)

Pavement Removals (East Jefferson St)

Next Week:

Phase 1A Washington Street

Monday 9/8 to Friday 9/12 – Contractor to continue paving operations on East Washington Street and into intersection of Washington Street and Main Street.

Phase 1B Main Street/Jefferson Street

Monday 9/8 to Friday 9/12:

Main Street: Contractor to make final water main tie in and continue sanitary sewer service installations along Main Street.

East Jefferson: Contractor to continue pavement removals on East Jefferson Street. Alliant will begin replacing gas lines.

*Please note – Sections of sidewalk along Main Street will be inaccessible as sanitary service installation is underway.

Looking Ahead:

Washington Street has been opened for use to the intersection. East Washington Street will remain closed for paving operations. Main Street and the intersection of Main Street and Jefferson Street will remain closed for utility installation.

DIGGIN DOWNTOWN UPDATE - 9/8Date: September 5, 2025 Recent Weeks: Underground Utility Service Installation (Main St) Paving Operations (East Washington St) Pavement...
Fall Flavor + Prizes = The Best Week Ever!Mark your calendars, food lovers,Restaurant Week is coming to Osceola from Monday, September 15 through Sunday, September 21!This is you...
DIGGIN DOWNTOWN UPDATE - 8/29Date: August 29, 2025 Recent Weeks: Underground Utility Service Installation (Main St) Paving Operations (East Washington St) Fillmore a...
DIGGIN DOWNTOWN UPDATE - 8/22Date: August 22, 2025 Recent Weeks: Pavement Removals (Jefferson & Main Intersection) Underground Utility Installation (Main St) Subgrad...