DIGGIN DOWNTOWN UPDATE - 9/8

Last Updated 9/8/2025Posted in DIGGIN' DOWNTOWN

Date: September 5, 2025

Recent Weeks:

Underground Utility Service Installation (Main St)

Paving Operations (East Washington St)

Pavement Removals (East Jefferson St)

Next Week:

Phase 1A Washington Street

Monday 9/8 to Friday 9/12 – Contractor to continue paving operations on East Washington Street and into intersection of Washington Street and Main Street.

Phase 1B Main Street/Jefferson Street

Monday 9/8 to Friday 9/12:

Main Street: Contractor to make final water main tie in and continue sanitary sewer service installations along Main Street.

East Jefferson: Contractor to continue pavement removals on East Jefferson Street. Alliant will begin replacing gas lines.

*Please note – Sections of sidewalk along Main Street will be inaccessible as sanitary service installation is underway.

Looking Ahead:

Washington Street has been opened for use to the intersection. East Washington Street will remain closed for paving operations. Main Street and the intersection of Main Street and Jefferson Street will remain closed for utility installation.

DIGGIN DOWNTOWN UPDATE - 12/19Date: December 19, 2025 Recent Weeks: Underground Utility Service installation (Jefferson St) Sidewalk Installation (Main St/East Jeffer...
DIGGIN DOWNTOWN UPDATE - 12/12/25Date: December 12, 2025 Recent Weeks: Underground Utility Service Installation (W. Jefferson St) Paving Operations (Main St/East Jeffers...
Christmas in the Park Brings Holiday Magic to Downtown O... Downtown Osceola came to life on Saturday, December 6, as families, friends, and visitors gathered to celebrate one of our favorite comm...
DIGGIN DOWNTOWN UPDATE - 12/5Date: December 5, 2025 Recent Weeks: Underground Utility Service Installation (Jefferson St) Paving Operations (Main St/Jefferson St) Ne...