DIGGIN DOWNTOWN UPDATE - 9/8

Last Updated 9/8/2025Posted in DIGGIN' DOWNTOWN

Date: September 5, 2025

Recent Weeks:

Underground Utility Service Installation (Main St)

Paving Operations (East Washington St)

Pavement Removals (East Jefferson St)

Next Week:

Phase 1A Washington Street

Monday 9/8 to Friday 9/12 – Contractor to continue paving operations on East Washington Street and into intersection of Washington Street and Main Street.

Phase 1B Main Street/Jefferson Street

Monday 9/8 to Friday 9/12:

Main Street: Contractor to make final water main tie in and continue sanitary sewer service installations along Main Street.

East Jefferson: Contractor to continue pavement removals on East Jefferson Street. Alliant will begin replacing gas lines.

*Please note – Sections of sidewalk along Main Street will be inaccessible as sanitary service installation is underway.

Looking Ahead:

Washington Street has been opened for use to the intersection. East Washington Street will remain closed for paving operations. Main Street and the intersection of Main Street and Jefferson Street will remain closed for utility installation.

Diggin Downtown Update - 10/17Date: October 17, 2025 Recent Weeks: Underground Utility Service installation (Main St/Jefferson St) Curb and Gutter installation (Main ...
Halloween Happenings: Frights, Fun, and Festivities Await! Spooky season is creeping in… and Osceola is brewing up a fang-tastic lineup of Halloween fun for all ages! From family trick-or-treatin...
Diggin Downtown Update - 10/10Date: October 10, 2025 Recent Weeks: Underground Utility Service Installation (East Jefferson St) Lighting System Installation (Washingt...
A New Chapter Begins at The Velvet Nook & RoastDowntown Osceola is turning the page on something truly special! On Tuesday, September 30, we gathered to celebrate the ribbon cutting a...