DIGGIN DOWNTOWN UPDATE - 9/19

Last Updated 9/26/2025Posted in DIGGIN' DOWNTOWN

Date: September 19, 2025

Recent Weeks:
Underground Utility Service installation (Main) St/Jefferson St)
Paving Operations (Main St/Washington St)
Sidewalk Installation (Main St) Next Week:

Phase 1A Washington Street/Main Street Monday 9/22 to Friday 9/26 – Contractor to work on subgrade prep and paving operations for Main Street road. Contractor to continue paving operations at the Washington/Main Street intersection. Phase 1B Main Street/Jefferson Street.
Monday 9/22 to Friday 9/26 – Contractor to continue utility installation at the intersection of Main Street and Jefferson Street and down East Jefferson Street.

Looking Ahead:
Main Street will remain closed from the Jefferson Street intersection to the Washington Street intersection. East Jefferson will remain closed for utility installation.
Diggin Downtown Update - 10/17Date: October 17, 2025 Recent Weeks: Underground Utility Service installation (Main St/Jefferson St) Curb and Gutter installation (Main ...
Halloween Happenings: Frights, Fun, and Festivities Await! Spooky season is creeping in… and Osceola is brewing up a fang-tastic lineup of Halloween fun for all ages! From family trick-or-treatin...
Diggin Downtown Update - 10/10Date: October 10, 2025 Recent Weeks: Underground Utility Service Installation (East Jefferson St) Lighting System Installation (Washingt...
A New Chapter Begins at The Velvet Nook & RoastDowntown Osceola is turning the page on something truly special! On Tuesday, September 30, we gathered to celebrate the ribbon cutting a...