DIGGIN' DOWNTOWN UPDATE - 9/26

Last Updated 9/26/2025Posted in DIGGIN' DOWNTOWN

Date: September 26, 2025 

Recent Weeks:
Underground Utility Service Installation (Main St/Jefferson St)
Water Main Installation (E Jefferson St)
Paving Operations (Main St/Washington St)
Light Pole Base Installation (Main Street)

Next Week:
Phase 1A Washington Street/Main Street
Monday 9/29 to Friday 10/3 – Contractor to continue paving operations along Main Street.
Phase 1B Main Street/Jefferson Street.
Monday 9/29 to Friday 10/3 – Contractor to continue utility installation at the intersection of Main Street and Jefferson Street and down East Jefferson Street.

Looking Ahead:
Main Street will remain closed from the Jefferson Street intersection to the Washington Street intersection for paving operations. East Jefferson will remain closed for utility installation.
Ribbon Cutting Celebration at Cuban FlavorFriday, September 26, Osceola Chamber Main Street celebrated a ribbon-cutting at Cuban Flavor! Guests enjoyed a festive atmosphere as we...
DIGGIN' DOWNTOWN UPDATE - 9/26Date: September 26, 2025 Recent Weeks: Underground Utility Service Installation (Main St/Jefferson St) Water Main Installation (E Jeffer...
DIGGIN DOWNTOWN UPDATE - 9/19Date: September 19, 2025 Recent Weeks: Underground Utility Service installation (Main) St/Jefferson St) Paving Operations (Main St/Washi...
September in Osceola: Food, Fun & Fall Vibes!As summer fades and the crispness of fall rolls in, Osceola comes alive with a calendar full of can’t-miss events. This September, the t...