DIGGIN' DOWNTOWN UPDATE - 9/26
Date: September 26, 2025
Recent Weeks:
Underground Utility Service Installation (Main St/Jefferson St)
Water Main Installation (E Jefferson St)
Paving Operations (Main St/Washington St)
Light Pole Base Installation (Main Street)
Next Week:
Phase 1A Washington Street/Main Street
Monday 9/29 to Friday 10/3 – Contractor to continue paving operations along Main Street.
Phase 1B Main Street/Jefferson Street.
Monday 9/29 to Friday 10/3 – Contractor to continue utility installation at the intersection of Main Street and Jefferson Street and down East Jefferson Street.
Looking Ahead:
Main Street will remain closed from the Jefferson Street intersection to the Washington Street intersection for paving operations. East Jefferson will remain closed for utility installation.