DIGGIN DOWNTOWN UPDATE - 10/24
Date: October 24, 2025
Recent Weeks:
Underground Utility Service Installation (Main St/Jefferson St)
Curb and Gutter installation (Main St)
Permeable Paver installation (Main St)
Pavement Removals (Jefferson St)
Next Week:
Phase 1B Main Street
Monday 10/27 to Friday 10/31 – Contractor to complete permeable paver installation and continue sidewalk installation on Main Street.
Phase 1B Main Street/East Jefferson Street.
Monday 10/27 to Friday 10/31 – Contractor to complete storm sewer installation in the intersection and continue water and sanitary sewer installation along East Jefferson Street
Phase 2A Jefferson Street.
Monday 10/27 to Friday 10/31 – Contractor to continue pavement removals along Jefferson Street up to the intersection with Fillmore Street
Looking Ahead:
Main Street and the intersection of Main Street and Jefferson Street will remain closed for utility installation. Jefferson Street between Main Street and Fillmore Street will remain closed for pavement removal.