DIGGIN DOWNTOWN UPDATE - 11/7

Last Updated 11/10/2025Posted in DIGGIN' DOWNTOWN

Date: November 7, 2025

Recent Weeks:

Underground Utility Service Installation (Jefferson St)

Permeable Paver installation (Main St)

Sidewalk Installation (Main Street)

Next Week:

Phase 1B Main Street/East Jefferson Street Intersection.

Monday 11/10 to Friday 11/14 – Contractor to begin earthwork, compaction, and subdrain installation.

Phase 2A Jefferson Street.

Monday 11/10 to Friday 11/14 Contractor to continue water main installation.

Looking Ahead:

East Jefferson to the Main Street intersection to remain closed for pavement operations. Jefferson Street between Main Street and Fillmore Street will remain closed for utility installation.

DIGGIN DOWNTOWN UPDATE - 12/19Date: December 19, 2025 Recent Weeks: Underground Utility Service installation (Jefferson St) Sidewalk Installation (Main St/East Jeffer...
DIGGIN DOWNTOWN UPDATE - 12/12/25Date: December 12, 2025 Recent Weeks: Underground Utility Service Installation (W. Jefferson St) Paving Operations (Main St/East Jeffers...
Christmas in the Park Brings Holiday Magic to Downtown O... Downtown Osceola came to life on Saturday, December 6, as families, friends, and visitors gathered to celebrate one of our favorite comm...
DIGGIN DOWNTOWN UPDATE - 12/5Date: December 5, 2025 Recent Weeks: Underground Utility Service Installation (Jefferson St) Paving Operations (Main St/Jefferson St) Ne...