DIGGIN DOWNTOWN UPDATE - 11/7
Date: November 7, 2025
Recent Weeks:
Underground Utility Service Installation (Jefferson St)
Permeable Paver installation (Main St)
Sidewalk Installation (Main Street)
Next Week:
Phase 1B Main Street/East Jefferson Street Intersection.
Monday 11/10 to Friday 11/14 – Contractor to begin earthwork, compaction, and subdrain installation.
Phase 2A Jefferson Street.
Monday 11/10 to Friday 11/14 – Contractor to continue water main installation.
Looking Ahead:
East Jefferson to the Main Street intersection to remain closed for pavement operations. Jefferson Street between Main Street and Fillmore Street will remain closed for utility installation.


.jpg)