Diggin Downtown Update - 11/14

Last Updated 11/24/2025Posted in DIGGIN' DOWNTOWN

Date: November 14, 2025 
Recent Weeks:
Underground Utility Service Installation (W Jefferson St)
Subgrade Compaction, Subbase and Subdrain Installation (Main St/E Jefferson St)

Next Week:
Phase 1B Main Street/East Jefferson Street Intersection.
Monday 11/17 to Friday 11/21 – Contractor to continue earthwork, compaction, subdrain installation, and paving operations.
Phase 2A Jefferson Street.
Monday 11/17 to Friday 11/21 – Contractor to work on water service installation.

Looking Ahead:
East Jefferson and the intersection of Main Street and Jefferson Street will remain closed for paving operations. Jefferson Street between Main Street and Fillmore Street will remain closed for utility installation.
DIGGIN DOWNTOWN UPDATE - 2/20/26Date: February 20, 2026 Recent Weeks: Water Man Installation (Fillmore St) Pavement Removal (Fillmore St) Paving Preparation and Install...
DIGGIN DOWNTOWN UPDATE - 2/16/26Date: February 13, 2026 Recent Weeks: Water Main Installation (Fillmore St) Pavement Removal (Fillmore St) Paving Preparation and Instal...
Ribbon Cutting Celebration: Welcome Vic’s Wash HouseOn February 3, we were proud to welcome Vic’s Wash House to Osceola’s Main Street with a ribbon cutting celebration. It was a great oppo...
Osceola175 - Osceola's Historic DepotAs Osceola celebrates 175 years of community, progress, and connection, our Glimpses of the Past series highlights places and stories th...