DIGGIN DOWNTOWN UPDATE - 1/23/26
Date: January 23, 2026
Recent Weeks:
Sanitary Sewer Installation (Jefferson St)
Pavement Preparation and Installation (Jefferson St)
Street Light Installation (Main Street)
Next Week:
Phase 2A Jefferson Street.
Monday 1/26 to Friday 1/30– Contractor to continue sanitary sewer installation. Paving activities will be halted until temperatures rise.
Looking Ahead:
Jefferson Street between Main Street and Fillmore Street will remain closed for utility and roadway installation.