DIGGIN DOWNTOWN UPDATE - 3/30

Last Updated 3/30/2026Posted in DIGGIN' DOWNTOWN

Date: March 27, 2026

Recent Weeks:

Storm Sewer Installation (Fillmore St)

Curb and Gutter Installation (Jefferson St)

Permeable Paver Installation (Jefferson St)

Sidewalk Installation (Jefferson St)

Next Week:

Phase 2A Jefferson Street.

Monday 3/30 to Friday 4/3:

·         Install permeable pavers south side of Jefferson Street.

·         Install remaining sections of sidewalk.

·         Install streetlight bases.

Phase 2B Fillmore Street.

Monday 3/30 to Friday 4/3:

·         Continue storm sewer installation.

·         Begin removal of pavement in Fillmore Jefferson intersection.

Looking Ahead:

Jefferson Street and Fillmore Street will remain closed for roadway/utility installation.


DIGGIN DOWNTOWN UPDATE - 3/30Date: March 27, 2026 Recent Weeks: Storm Sewer Installation (Fillmore St) Curb and Gutter Installation (Jefferson St) Permeable Paver In...
DIGGIN DOWNTOWN UPDATE - 3/20Date: March 20, 2026 Recent Weeks: Storm Sewer Installation (Fillmore St) Curb and Gutter Installation (Jefferson St) Permeable Paver In...
DIGGIN DOWNTOWN UPDATE - 3/13Date: March 13, 2026 Recent Weeks: Sanitary Sewer Service Installation (Fillmore St) Storm Sewer Installation (Fillmore St) Curb and Gut...
Celebrating Community at the Greater Osceola Partnership... On Friday, March 6, the Greater Osceola Partnership Annual Dinner was held, in partnership with the Osceola Chamber Main Street and Clar...