DIGGIN' DOWNTOWN UPDATE - 3/7
Date: March 7, 2025
Recent Weeks:
Water Main Installation
Pavement Removal
Next Week:
Phase 1A Washington Street
Monday 3/10 – Contractor will begin installing water services along Washington Street on the west side of Fillmore Street.
Tuesday 3/11 – Contractor will complete installation of water services along Washington Street on the west side of Filmore Street. Contractor to begin sidewalk removals in front of fire station to complete fire station water service installation.
Wednesday 3/12 to Friday 3/14 – Contractor to begin sidewalk removals and water service installations in front of businesses on north side of Washington Street.
*Please Note –Sections of sidewalk will be temporarily inaccessible during water service installation.
Looking Ahead:
Washington Street will remain closed as utility installation continues through the following weeks.
Follow along here to see the latest progress!
Project Facebook Page:
https://www.facebook.com/DowntownOsceolaStreetscapeProject/