DIGGIN' DOWNTOWN UPDATE - 3/7

Last Updated 4/4/2025Posted in DIGGIN' DOWNTOWN

Date: March 7, 2025

Recent Weeks:

Water Main Installation

Pavement Removal

Next Week:

Phase 1A Washington Street

Monday 3/10 – Contractor will begin installing water services along Washington Street on the west side of Fillmore Street.

Tuesday 3/11 – Contractor will complete installation of water services along Washington Street on the west side of Filmore Street. Contractor to begin sidewalk removals in front of fire station to complete fire station water service installation.

Wednesday 3/12 to Friday 3/14 – Contractor to begin sidewalk removals and water service installations in front of businesses on north side of Washington Street.

*Please Note –Sections of sidewalk will be temporarily inaccessible during water service installation.

Looking Ahead:

Washington Street will remain closed as utility installation continues through the following weeks.

Follow along here to see the latest progress!

Project Facebook Page:

https://www.facebook.com/DowntownOsceolaStreetscapeProject/


DIGGIN' DOWNTOWN UPDATE - 6/6Date: June 6, 2025 Recent Weeks: Subdrain Installation (Washington St) Concrete Paving Operations (Washington St) Storm Sewer installati...
DIGGIN' DOWNTOWN UPDATE - 5/30Date: May 30, 2025 Recent Weeks: Subdrain Installation (Washington St) Concrete Paving Operations (Washington St) Next Week: Phase 1A Wa...
DIGGIN' DOWNTOWN UPDATE - 5/23Date: May 23, 2025 Recent Weeks: Subdrain Installation (Washington St) Concrete Paving Operations (Washington St) Pavement Removals (Mai...
Welcome to Osceola, Droppett! | Ribbon Cutting + Coffee... On May 15,we had the pleasure of officially welcoming Droppett to Osceola with a celebratory Ribbon Cutting and Coffee Connections event...