DIGGIN' DOWNTOWN UPDATE - 2/27

Last Updated 3/3/2026Posted in DIGGIN' DOWNTOWN

Date: February 27, 2026 
Recent Weeks:
Water Service Installation (Fillmore St)
Paving Preparation and Installation (Jefferson St)

Next Week:
Phase 2A Jefferson Street.
Monday 3/2 to Friday 3/6 – Contractor to continue permeable paver installation, sidewalk paving, and curb and gutter installation.

Phase 2B Fillmore Street.
Monday 3/2 to Friday 3/6 – Contractor to complete water service installation and begin working on sanitary service installations.

Looking Ahead:
Jefferson Street and Fillmore Street will remain closed for roadway/utility installation.
DIGGIN DOWNTOWN UPDATE - 3/30Date: March 27, 2026 Recent Weeks: Storm Sewer Installation (Fillmore St) Curb and Gutter Installation (Jefferson St) Permeable Paver In...
DIGGIN DOWNTOWN UPDATE - 3/20Date: March 20, 2026 Recent Weeks: Storm Sewer Installation (Fillmore St) Curb and Gutter Installation (Jefferson St) Permeable Paver In...
DIGGIN DOWNTOWN UPDATE - 3/13Date: March 13, 2026 Recent Weeks: Sanitary Sewer Service Installation (Fillmore St) Storm Sewer Installation (Fillmore St) Curb and Gut...