DIGGIN' DOWNTOWN UPDATE - 2/7

Last Updated 4/4/2025Posted in DIGGIN' DOWNTOWN

Date: February 7, 2025

Recent Weeks:

Water Main Installation.

Light poles to be removed.

Connect new water line to both hydrants.


Next Week:

Mon-Wed testing water main

Thursday, February 13 all of Washington Street to be closed for remainder of Washington Street project.

Pavement removal to begin on February 13 to prepare for watermain service connections to buildings.

 

Looking Ahead:

Week of February 17 new watermain services to be connected to buildings.  This will involve partial sidewalk removal with rock to back fill the area once completed.

 After the water services to the buildings’ are complete they will start on the storm system.

Follow along here to see the latest progress!
Project Facebook Page:
https://www.facebook.com/DowntownOsceolaStreetscapeProject/
Main Street Closure and Washinton Street Progress: What’... Significant progress is underway in downtown as infrastructure improvements continue to move forward along Washington Street. Crews have...
DIGGIN' DOWNTOWN UPDATE - 4/25Date: April 25, 2025 Recent Weeks: Storm Sewer Installation Next Week: Phase 1A Washington Street Monday 4/28 to Friday 5/2 – Contractor...
DIGGIN' DOWNTOWN UPDATE - 4/18Date: April 18, 2025 Recent Weeks: Storm Sewer Installation Sidewalk Installation ADA Accessible Ramps Poured Next Week: Phase 1A Washin...
DIGGIN' DOWNTOWN UPDATE - 4/11Date: April 11, 2025 This Past Week: Storm Sewer Installation Sidewalk Installation Next Week: Phase 1A Washington Street Monday 4/14 to...