DIGGIN' DOWNTOWN UPDATE - 2/21

Last Updated 7/21/2025Posted in DIGGIN' DOWNTOWN

Date: February 21, 2025

Recent Weeks:

-Water Main Installation

-No work week (2/17) due to low temperatures

Next Week:

Phase 1A Washington Street

Monday 2/24: The contractor will mobilize on site to prepare for additional demolition of Washington Street.

Tuesday 2/25: Washington Street will be closed to all traffic. Pavement removal will begin on the North half of Washington Street.

Wednesday – Friday 2/26-2/28: Pavement removal will continue. The contractor will begin installing water services to the buildings along Washington Street.

*Please NoteSections of sidewalk along the north side of Washington Street will be temporarily inaccessible during water service installation.

Looking Ahead:

Washington Street will remain closed as water main and service installation along Washington Street continues through the following weeks.

Follow along here to see the latest progress!

Project Facebook Page:

https://www.facebook.com/DowntownOsceolaStreetscapeProject/

DIGGIN DOWNTOWN UPDATE - 12/19Date: December 19, 2025 Recent Weeks: Underground Utility Service installation (Jefferson St) Sidewalk Installation (Main St/East Jeffer...
DIGGIN DOWNTOWN UPDATE - 12/12/25Date: December 12, 2025 Recent Weeks: Underground Utility Service Installation (W. Jefferson St) Paving Operations (Main St/East Jeffers...
Christmas in the Park Brings Holiday Magic to Downtown O... Downtown Osceola came to life on Saturday, December 6, as families, friends, and visitors gathered to celebrate one of our favorite comm...
DIGGIN DOWNTOWN UPDATE - 12/5Date: December 5, 2025 Recent Weeks: Underground Utility Service Installation (Jefferson St) Paving Operations (Main St/Jefferson St) Ne...