DIGGIN' DOWNTOWN UPDATE - 2/21

Last Updated 7/21/2025Posted in DIGGIN' DOWNTOWN

Date: February 21, 2025

Recent Weeks:

-Water Main Installation

-No work week (2/17) due to low temperatures

Next Week:

Phase 1A Washington Street

Monday 2/24: The contractor will mobilize on site to prepare for additional demolition of Washington Street.

Tuesday 2/25: Washington Street will be closed to all traffic. Pavement removal will begin on the North half of Washington Street.

Wednesday – Friday 2/26-2/28: Pavement removal will continue. The contractor will begin installing water services to the buildings along Washington Street.

*Please NoteSections of sidewalk along the north side of Washington Street will be temporarily inaccessible during water service installation.

Looking Ahead:

Washington Street will remain closed as water main and service installation along Washington Street continues through the following weeks.

Follow along here to see the latest progress!

Project Facebook Page:

https://www.facebook.com/DowntownOsceolaStreetscapeProject/

DIGGIN DOWNTOWN UPDATE - 3/13Date: March 13, 2026 Recent Weeks: Sanitary Sewer Service Installation (Fillmore St) Storm Sewer Installation (Fillmore St) Curb and Gut...
Celebrating Community at the Greater Osceola Partnership... On Friday, March 6, the Greater Osceola Partnership Annual Dinner was held, in partnership with the Osceola Chamber Main Street and Clar...
DIGGIN DOWNTOWN 3/6Date: March 6, 2026 Recent Weeks: Water Service Installation (Fillmore St) Sanitary Sewer Service Installation (Fillmore St) Paving Prep...
DIGGIN' DOWNTOWN UPDATE - 2/27Date: February 27, 2026 Recent Weeks: Water Service Installation (Fillmore St) Paving Preparation and Installation (Jefferson St) Next W...