DIGGIN' DOWNTOWN UPDATE - 2/21
Date: February 21, 2025
Recent Weeks:
-Water Main Installation
-No work week (2/17) due to low temperatures
Next Week:
Phase 1A Washington Street
Monday 2/24: The contractor will mobilize on site to prepare for additional demolition of Washington Street.
Tuesday 2/25: Washington Street will be closed to all traffic. Pavement removal will begin on the North half of Washington Street.
Wednesday – Friday 2/26-2/28: Pavement removal will continue. The contractor will begin installing water services to the buildings along Washington Street.
*Please Note –Sections of sidewalk along the north side of Washington Street will be temporarily inaccessible during water service installation.
Looking Ahead:
Washington Street will remain closed as water main and service installation along Washington Street continues through the following weeks.
Follow along here to see the latest progress!