DIGGIN' DOWNTOWN UPDATE - 2/21

Last Updated 4/4/2025Posted in DIGGIN' DOWNTOWN

Date: February 21, 2025

Recent Weeks:

-Water Main Installation

-No work week (2/17) due to low temperatures

Next Week:

Phase 1A Washington Street

Monday 2/24: The contractor will mobilize on site to prepare for additional demolition of Washington Street.

Tuesday 2/25: Washington Street will be closed to all traffic. Pavement removal will begin on the North half of Washington Street.

Wednesday – Friday 2/26-2/28: Pavement removal will continue. The contractor will begin installing water services to the buildings along Washington Street.

*Please NoteSections of sidewalk along the north side of Washington Street will be temporarily inaccessible during water service installation.

Looking Ahead:

Washington Street will remain closed as water main and service installation along Washington Street continues through the following weeks.

Follow along here to see the latest progress!

Project Facebook Page:

https://www.facebook.com/DowntownOsceolaStreetscapeProject/

Main Street Closure and Washinton Street Progress: What’... Significant progress is underway in downtown as infrastructure improvements continue to move forward along Washington Street. Crews have...
DIGGIN' DOWNTOWN UPDATE - 4/25Date: April 25, 2025 Recent Weeks: Storm Sewer Installation Next Week: Phase 1A Washington Street Monday 4/28 to Friday 5/2 – Contractor...
DIGGIN' DOWNTOWN UPDATE - 4/18Date: April 18, 2025 Recent Weeks: Storm Sewer Installation Sidewalk Installation ADA Accessible Ramps Poured Next Week: Phase 1A Washin...
DIGGIN' DOWNTOWN UPDATE - 4/11Date: April 11, 2025 This Past Week: Storm Sewer Installation Sidewalk Installation Next Week: Phase 1A Washington Street Monday 4/14 to...