DIGGIN' DOWNTOWN UPDATE - 2/21

Last Updated 7/21/2025Posted in DIGGIN' DOWNTOWN

Date: February 21, 2025

Recent Weeks:

-Water Main Installation

-No work week (2/17) due to low temperatures

Next Week:

Phase 1A Washington Street

Monday 2/24: The contractor will mobilize on site to prepare for additional demolition of Washington Street.

Tuesday 2/25: Washington Street will be closed to all traffic. Pavement removal will begin on the North half of Washington Street.

Wednesday – Friday 2/26-2/28: Pavement removal will continue. The contractor will begin installing water services to the buildings along Washington Street.

*Please NoteSections of sidewalk along the north side of Washington Street will be temporarily inaccessible during water service installation.

Looking Ahead:

Washington Street will remain closed as water main and service installation along Washington Street continues through the following weeks.

Follow along here to see the latest progress!

Project Facebook Page:

https://www.facebook.com/DowntownOsceolaStreetscapeProject/

Osceola Chamber Main Street Lights Up Downtown with New ... Osceola Chamber Main Street has taken another bold step in transforming the heart of downtown into a vibrant, welcoming destination. The...
DIGGIN DOWNTOWN UPDATE - 8/8Date: August 8, 2025 Recent Weeks: Concrete Paving Operations (Washington & Main St) Underground Utility Installation (Washington Street...
DIGGIN DOWNTOWN UPDATE - 7/25Date: July 25, 2025 Recent Weeks: Concrete Paving Operations (Washington St) Permeable Paver Installation (Washington St) Storm Sewer in...
DIGGIN' DOWNTOWN CONSTRUCITON SCHEDULE OVERVIEWRemainder of July East Washington utility work Washington street pavers and concrete operations Subgrade prep on Main/Washington Interse...