DIGGIN' DOWNTOWN UPDATE - 3-28

Last Updated 7/21/2025Posted in DIGGIN' DOWNTOWN

Date: March 28, 2025

Recent Weeks:

-Sanitary sewer service installation

-Water main installation and water main services completed on Washington Street.

Next Week:

Phase 1A Washington Street

-Monday 3/31 to Wednesday 4/2 – Contractor will finish sanitary sewer service installations as well as replace existing sanitary sewer manholes along Washington Street.

-Thursday 4/3 to Friday 4/4 – Contractor will begin storm sewer installation along Washington Street.

-Sidewalk preparation may begin this week, contingent upon the completion of sanitary sewer installations.

Looking Ahead:

-Washington Street will remain closed as storm sewer installation continues through the following weeks.

- Main Street is expected to close within the next 3-4 weeks following the completion of the storm sewer installation.

Follow along here to see the latest progress!

Project Facebook Page:

https://www.facebook.com/DowntownOsceolaStreetscapeProject/

Osceola Chamber Main Street Lights Up Downtown with New ... Osceola Chamber Main Street has taken another bold step in transforming the heart of downtown into a vibrant, welcoming destination. The...
DIGGIN DOWNTOWN UPDATE - 8/8Date: August 8, 2025 Recent Weeks: Concrete Paving Operations (Washington & Main St) Underground Utility Installation (Washington Street...
DIGGIN DOWNTOWN UPDATE - 7/25Date: July 25, 2025 Recent Weeks: Concrete Paving Operations (Washington St) Permeable Paver Installation (Washington St) Storm Sewer in...
DIGGIN' DOWNTOWN CONSTRUCITON SCHEDULE OVERVIEWRemainder of July East Washington utility work Washington street pavers and concrete operations Subgrade prep on Main/Washington Interse...