DIGGIN' DOWNTOWN UPDATE - 3-28

Last Updated 4/4/2025Posted in DIGGIN' DOWNTOWN

Date: March 28, 2025

Recent Weeks:

-Sanitary sewer service installation

-Water main installation and water main services completed on Washington Street.

Next Week:

Phase 1A Washington Street

-Monday 3/31 to Wednesday 4/2 – Contractor will finish sanitary sewer service installations as well as replace existing sanitary sewer manholes along Washington Street.

-Thursday 4/3 to Friday 4/4 – Contractor will begin storm sewer installation along Washington Street.

-Sidewalk preparation may begin this week, contingent upon the completion of sanitary sewer installations.

Looking Ahead:

-Washington Street will remain closed as storm sewer installation continues through the following weeks.

- Main Street is expected to close within the next 3-4 weeks following the completion of the storm sewer installation.

Follow along here to see the latest progress!

Project Facebook Page:

https://www.facebook.com/DowntownOsceolaStreetscapeProject/

Main Street Closure and Washinton Street Progress: What’... Significant progress is underway in downtown as infrastructure improvements continue to move forward along Washington Street. Crews have...
DIGGIN' DOWNTOWN UPDATE - 4/25Date: April 25, 2025 Recent Weeks: Storm Sewer Installation Next Week: Phase 1A Washington Street Monday 4/28 to Friday 5/2 – Contractor...
DIGGIN' DOWNTOWN UPDATE - 4/18Date: April 18, 2025 Recent Weeks: Storm Sewer Installation Sidewalk Installation ADA Accessible Ramps Poured Next Week: Phase 1A Washin...
DIGGIN' DOWNTOWN UPDATE - 4/11Date: April 11, 2025 This Past Week: Storm Sewer Installation Sidewalk Installation Next Week: Phase 1A Washington Street Monday 4/14 to...