Date: March 28, 2025

Recent Weeks:

-Sanitary sewer service installation

-Water main installation and water main services completed on Washington Street.

Next Week:

Phase 1A Washington Street

-Monday 3/31 to Wednesday 4/2 – Contractor will finish sanitary sewer service installations as well as replace existing sanitary sewer manholes along Washington Street.

-Thursday 4/3 to Friday 4/4 – Contractor will begin storm sewer installation along Washington Street.

-Sidewalk preparation may begin this week, contingent upon the completion of sanitary sewer installations.

Looking Ahead:

-Washington Street will remain closed as storm sewer installation continues through the following weeks.

- Main Street is expected to close within the next 3-4 weeks following the completion of the storm sewer installation.

Follow along here to see the latest progress!

Project Facebook Page:

https://www.facebook.com/DowntownOsceolaStreetscapeProject/

DIGGIN DOWNTOWN UPDATE - 3/13Date: March 13, 2026 Recent Weeks: Sanitary Sewer Service Installation (Fillmore St) Storm Sewer Installation (Fillmore St) Curb and Gut...
Celebrating Community at the Greater Osceola Partnership... On Friday, March 6, the Greater Osceola Partnership Annual Dinner was held, in partnership with the Osceola Chamber Main Street and Clar...
DIGGIN DOWNTOWN 3/6Date: March 6, 2026 Recent Weeks: Water Service Installation (Fillmore St) Sanitary Sewer Service Installation (Fillmore St) Paving Prep...
DIGGIN' DOWNTOWN UPDATE - 2/27Date: February 27, 2026 Recent Weeks: Water Service Installation (Fillmore St) Paving Preparation and Installation (Jefferson St) Next W...