DIGGIN' DOWNTOWN UPDATE - 3/21
Date: March 21, 2025
Recent Weeks:
Water main and service installation.
Light poles on Washington Street Removed.
Washington Street watermain connected to Main Street waterline to maintain water pressure and fire flows throughout the city.
This Week:
Phase 1A Washington Street
Monday 3/24 – Contractor completed final water main tie in at west end of Washington Street.
Tuesday 3/25 to Friday 3/28 – Contractor will install new sanitary sewer services along Washington Street.
Looking Ahead:
Washington Street will remain closed as sanitary and storm sewer installation continues through the following weeks.
New sidewalks are expected to be installed mid-week next week along the building fronts.
Follow along here to see the latest progress!
Project Facebook Page:
https://www.facebook.com/DowntownOsceolaStreetscapeProject/