DIGGIN' DOWNTOWN UPDATE - 3/21

Last Updated 7/21/2025Posted in DIGGIN' DOWNTOWN

Date: March 21, 2025

Recent Weeks:

Water main and service installation.

Light poles on Washington Street Removed.

Washington Street watermain connected to Main Street waterline to maintain water pressure and fire flows throughout the city.

This Week:

Phase 1A Washington Street

Monday 3/24 – Contractor completed final water main tie in at west end of Washington Street.

Tuesday 3/25 to Friday 3/28 – Contractor will install new sanitary sewer services along Washington Street.

Looking Ahead:

Washington Street will remain closed as sanitary and storm sewer installation continues through the following weeks.

New sidewalks are expected to be installed mid-week next week along the building fronts.

Follow along here to see the latest progress!

Project Facebook Page:

https://www.facebook.com/DowntownOsceolaStreetscapeProject/


Osceola Chamber Main Street Lights Up Downtown with New ... Osceola Chamber Main Street has taken another bold step in transforming the heart of downtown into a vibrant, welcoming destination. The...
DIGGIN DOWNTOWN UPDATE - 8/8Date: August 8, 2025 Recent Weeks: Concrete Paving Operations (Washington & Main St) Underground Utility Installation (Washington Street...
DIGGIN DOWNTOWN UPDATE - 7/25Date: July 25, 2025 Recent Weeks: Concrete Paving Operations (Washington St) Permeable Paver Installation (Washington St) Storm Sewer in...
DIGGIN' DOWNTOWN CONSTRUCITON SCHEDULE OVERVIEWRemainder of July East Washington utility work Washington street pavers and concrete operations Subgrade prep on Main/Washington Interse...