DIGGIN' DOWNTOWN UPDATE - 4/4

Last Updated 9/26/2025Posted in DIGGIN' DOWNTOWN

Date: April 4, 2025

Recent Weeks:

Sanitary Sewer Installation

Manhole Installation

Pavement Removal

Next Week:

Phase 1A Washington Street

Monday 4/7 to Tuesday 4/8 – Contractor to begin storm sewer installation along Washington Street.

Wednesday 4/9 to Friday 4/11 – Contractor will continue storm sewer installation along Washington Street, as well as begin preparation for sidewalk installation on the north side of Washington Street.

Looking Ahead:

Washington Street will remain closed as storm sewer installation continues through the following weeks.

Contractor will move to Main Street to install new water main once storm sewer installation is complete.

Follow along here to see the latest progress!

Project Facebook Page:

https://www.facebook.com/DowntownOsceolaStreetscapeProject/

DIGGIN DOWNTOWN UPDATE - 3/13Date: March 13, 2026 Recent Weeks: Sanitary Sewer Service Installation (Fillmore St) Storm Sewer Installation (Fillmore St) Curb and Gut...
Celebrating Community at the Greater Osceola Partnership... On Friday, March 6, the Greater Osceola Partnership Annual Dinner was held, in partnership with the Osceola Chamber Main Street and Clar...
DIGGIN DOWNTOWN 3/6Date: March 6, 2026 Recent Weeks: Water Service Installation (Fillmore St) Sanitary Sewer Service Installation (Fillmore St) Paving Prep...
DIGGIN' DOWNTOWN UPDATE - 2/27Date: February 27, 2026 Recent Weeks: Water Service Installation (Fillmore St) Paving Preparation and Installation (Jefferson St) Next W...