DIGGIN' DOWNTOWN UPDATE - 4/4

Last Updated 9/26/2025Posted in DIGGIN' DOWNTOWN

Date: April 4, 2025

Recent Weeks:

Sanitary Sewer Installation

Manhole Installation

Pavement Removal

Next Week:

Phase 1A Washington Street

Monday 4/7 to Tuesday 4/8 – Contractor to begin storm sewer installation along Washington Street.

Wednesday 4/9 to Friday 4/11 – Contractor will continue storm sewer installation along Washington Street, as well as begin preparation for sidewalk installation on the north side of Washington Street.

Looking Ahead:

Washington Street will remain closed as storm sewer installation continues through the following weeks.

Contractor will move to Main Street to install new water main once storm sewer installation is complete.

Follow along here to see the latest progress!

Project Facebook Page:

https://www.facebook.com/DowntownOsceolaStreetscapeProject/

DIGGIN DOWNTOWN UPDATE - 12/19Date: December 19, 2025 Recent Weeks: Underground Utility Service installation (Jefferson St) Sidewalk Installation (Main St/East Jeffer...
DIGGIN DOWNTOWN UPDATE - 12/12/25Date: December 12, 2025 Recent Weeks: Underground Utility Service Installation (W. Jefferson St) Paving Operations (Main St/East Jeffers...
Christmas in the Park Brings Holiday Magic to Downtown O... Downtown Osceola came to life on Saturday, December 6, as families, friends, and visitors gathered to celebrate one of our favorite comm...
DIGGIN DOWNTOWN UPDATE - 12/5Date: December 5, 2025 Recent Weeks: Underground Utility Service Installation (Jefferson St) Paving Operations (Main St/Jefferson St) Ne...