This Past Week:
Storm Sewer Installation
Sidewalk Installation
Next Week:
Phase 1A Washington Street
Monday 4/14 to Friday 4/18 – Contractor to continue storm sewer and sidewalk installations along Washington Street.
Looking Ahead:
Washington Street will remain closed as storm sewer installation continues through the following weeks.
Pavement preparation along Washington Street to begin after storm sewer installation. Contractor will move to Main Street to install new water main once storm sewer installation is complete.

Follow along here to see the latest progress!

Project Facebook Page:

https://www.facebook.com/DowntownOsceolaStreetscapeProject/

Osceola Chamber Main Street Lights Up Downtown with New ... Osceola Chamber Main Street has taken another bold step in transforming the heart of downtown into a vibrant, welcoming destination. The...
DIGGIN DOWNTOWN UPDATE - 8/8Date: August 8, 2025 Recent Weeks: Concrete Paving Operations (Washington & Main St) Underground Utility Installation (Washington Street...
DIGGIN DOWNTOWN UPDATE - 7/25Date: July 25, 2025 Recent Weeks: Concrete Paving Operations (Washington St) Permeable Paver Installation (Washington St) Storm Sewer in...
DIGGIN' DOWNTOWN CONSTRUCITON SCHEDULE OVERVIEWRemainder of July East Washington utility work Washington street pavers and concrete operations Subgrade prep on Main/Washington Interse...