DIGGIN' DOWNTOWN UPDATE - 4/11

Last Updated 4/14/2025Posted in DIGGIN' DOWNTOWN

Date: April 11, 2025
This Past Week:
Storm Sewer Installation
Sidewalk Installation
Next Week:
Phase 1A Washington Street
Monday 4/14 to Friday 4/18 – Contractor to continue storm sewer and sidewalk installations along Washington Street.
Looking Ahead:
Washington Street will remain closed as storm sewer installation continues through the following weeks.
Pavement preparation along Washington Street to begin after storm sewer installation. Contractor will move to Main Street to install new water main once storm sewer installation is complete.

Follow along here to see the latest progress!

Project Facebook Page:

https://www.facebook.com/DowntownOsceolaStreetscapeProject/

DIGGIN' DOWNTOWN UPDATE - 6/6Date: June 6, 2025 Recent Weeks: Subdrain Installation (Washington St) Concrete Paving Operations (Washington St) Storm Sewer installati...
DIGGIN' DOWNTOWN UPDATE - 5/30Date: May 30, 2025 Recent Weeks: Subdrain Installation (Washington St) Concrete Paving Operations (Washington St) Next Week: Phase 1A Wa...
DIGGIN' DOWNTOWN UPDATE - 5/23Date: May 23, 2025 Recent Weeks: Subdrain Installation (Washington St) Concrete Paving Operations (Washington St) Pavement Removals (Mai...
Welcome to Osceola, Droppett! | Ribbon Cutting + Coffee... On May 15,we had the pleasure of officially welcoming Droppett to Osceola with a celebratory Ribbon Cutting and Coffee Connections event...