DIGGIN' DOWNTOWN UPDATE - 4/18

Last Updated 4/21/2025Posted in DIGGIN' DOWNTOWN

Date: April 18, 2025

Recent Weeks:

Storm Sewer Installation

Sidewalk Installation

ADA Accessible Ramps Poured

Next Week:

Phase 1A Washington Street

Monday 4/21 to Friday 4/25 – Contractor to continue storm sewer installation along Washington Street.

Looking Ahead:

Washington Street will remain closed as storm sewer installation continues through the following weeks.

In the upcoming weeks Main Street will be closed for pavement removal.

Once the utility crew finishes installing the storm sewer along Washington Street, they will shift their focus to Main Street to begin installing the new water main. Meanwhile, on Washington Street TK Concrete will focus on surface improvements, including road preparation, pouring new pavement, completing the remaining sidewalks, and installing permeable pavers in the on-street parking areas.

Follow along here to see the latest progress!

DIGGIN' DOWNTOWN UPDATE - 6/6Date: June 6, 2025 Recent Weeks: Subdrain Installation (Washington St) Concrete Paving Operations (Washington St) Storm Sewer installati...
DIGGIN' DOWNTOWN UPDATE - 5/30Date: May 30, 2025 Recent Weeks: Subdrain Installation (Washington St) Concrete Paving Operations (Washington St) Next Week: Phase 1A Wa...
DIGGIN' DOWNTOWN UPDATE - 5/23Date: May 23, 2025 Recent Weeks: Subdrain Installation (Washington St) Concrete Paving Operations (Washington St) Pavement Removals (Mai...
Welcome to Osceola, Droppett! | Ribbon Cutting + Coffee... On May 15,we had the pleasure of officially welcoming Droppett to Osceola with a celebratory Ribbon Cutting and Coffee Connections event...