DIGGIN' DOWNTOWN UPDATE - 4/25

Last Updated 9/26/2025Posted in DIGGIN' DOWNTOWN

Date: April 25, 2025 

Recent Weeks:
Storm Sewer Installation

Next Week:
Phase 1A Washington Street
(Monday 4/28 to Friday 5/2) 
Contractor to continue storm sewer installation along Washington Street.
Looking Ahead: 
Washington Street will remain closed as storm sewer installation continues through the following weeks. After storm sewer installation has been completed the contractor will begin subgrade preparation.
In the upcoming weeks Main Street will be closed for pavement removal to allow for the installation of the new water main and water service lines to the buildings.
Ribbon Cutting Celebration at Cuban FlavorFriday, September 26, Osceola Chamber Main Street celebrated a ribbon-cutting at Cuban Flavor! Guests enjoyed a festive atmosphere as we...
DIGGIN' DOWNTOWN UPDATE - 9/26Date: September 26, 2025 Recent Weeks: Underground Utility Service Installation (Main St/Jefferson St) Water Main Installation (E Jeffer...
DIGGIN DOWNTOWN UPDATE - 9/19Date: September 19, 2025 Recent Weeks: Underground Utility Service installation (Main) St/Jefferson St) Paving Operations (Main St/Washi...
September in Osceola: Food, Fun & Fall Vibes!As summer fades and the crispness of fall rolls in, Osceola comes alive with a calendar full of can’t-miss events. This September, the t...