DIGGIN' DOWNTOWN UPDATE - 4/25

Last Updated 9/26/2025Posted in DIGGIN' DOWNTOWN

Date: April 25, 2025 

Recent Weeks:
Storm Sewer Installation

Next Week:
Phase 1A Washington Street
(Monday 4/28 to Friday 5/2) 
Contractor to continue storm sewer installation along Washington Street.
Looking Ahead: 
Washington Street will remain closed as storm sewer installation continues through the following weeks. After storm sewer installation has been completed the contractor will begin subgrade preparation.
In the upcoming weeks Main Street will be closed for pavement removal to allow for the installation of the new water main and water service lines to the buildings.
DIGGIN DOWNTOWN UPDATE - 12/19Date: December 19, 2025 Recent Weeks: Underground Utility Service installation (Jefferson St) Sidewalk Installation (Main St/East Jeffer...
DIGGIN DOWNTOWN UPDATE - 12/12/25Date: December 12, 2025 Recent Weeks: Underground Utility Service Installation (W. Jefferson St) Paving Operations (Main St/East Jeffers...
Christmas in the Park Brings Holiday Magic to Downtown O... Downtown Osceola came to life on Saturday, December 6, as families, friends, and visitors gathered to celebrate one of our favorite comm...
DIGGIN DOWNTOWN UPDATE - 12/5Date: December 5, 2025 Recent Weeks: Underground Utility Service Installation (Jefferson St) Paving Operations (Main St/Jefferson St) Ne...