DIGGIN' DOWNTOWN UPDATE - 4/25
Date: April 25, 2025
Recent Weeks:
Storm Sewer Installation
Next Week:
Phase 1A Washington Street
(Monday 4/28 to Friday 5/2)
Contractor to continue storm sewer installation along Washington Street.
Looking Ahead:
Washington Street will remain closed as storm sewer installation continues through the following weeks. After storm sewer installation has been completed the contractor will begin subgrade preparation.
In the upcoming weeks Main Street will be closed for pavement removal to allow for the installation of the new water main and water service lines to the buildings.