DIGGIN' DOWNTOWN UPDATE - 5/2
Date: May 2, 2025
Recent Weeks:
Storm Sewer Installation
Next Week:
Phase 1A Washington Street
Monday 5/5 to Tuesday 5/6 – Contractor to continue storm sewer installation on east side of Washington Street.
Wednesday 5/7 to Friday 5/9 – Contractor to begin subgrade preparation on east side of Washington Street while storm sewer installation is underway on west side of Washington Street.
Looking Ahead:
Washington Street will remain closed as storm sewer installation and paving preparation continues through the following weeks. Contractor tentatively plans to close Main Street to traffic beginning May 12 to begin pavement removals to allow for the installation of the new water main.