DIGGIN' DOWNTOWN UPDATE - 5/12
Date: May 9, 2025
Recent Weeks:
Storm Sewer Installation
Subgrade Preparation
Next Week:
Phase 1A Washington Street
Monday 5/12 to Friday 5/16 – Contractor to continue storm sewer installation on west side of Fillmore Street and subgrade preparation on east side of Washington Street. Contractor will begin installing subbase on east side of Washington Street toward the end of the week.
Phase 1B Main Street
Monday 5/12 – Main Street will be closed to traffic as the contractor begins pavement removals.
Looking Ahead:
Washington Street will remain closed as storm sewer installation and paving preparation continues through the following weeks.