DIGGIN' DOWNTOWN UPDATE - 5/12

Last Updated 7/21/2025Posted in DIGGIN' DOWNTOWN

Date: May 9, 2025

Recent Weeks:

Storm Sewer Installation

Subgrade Preparation

Next Week:

Phase 1A Washington Street

Monday 5/12 to Friday 5/16  – Contractor to continue storm sewer installation on west side of Fillmore Street and subgrade preparation on east side of Washington Street. Contractor will begin installing subbase on east side of Washington Street toward the end of the week.

Phase 1B Main Street

Monday 5/12 Main Street will be closed to traffic as the contractor begins pavement removals.

Looking Ahead:

Washington Street will remain closed as storm sewer installation and paving preparation continues through the following weeks.


Shop Local This Holiday Season: Osceola Has Something fo... The holiday season is officially here, and as we inch closer to Shop Small Saturday on November 29 , our local businesses are buzzing wi...
DIGGIN DOWNTOWN UPDATE - 11/7Date: November 7, 2025 Recent Weeks: Underground Utility Service Installation (Jefferson St) Permeable Paver installation (Main St) Side...
DIGGIN DOWNTOWN UPDATE - 10/31Date: October 31, 2025 Recent Weeks: Underground Utility Service Installation (Main St/E Jefferson St) Permeable Paver Installation (Mai...
DIGGIN DOWNTOWN UPDATE - 10/24Date: October 24, 2025 Recent Weeks: Underground Utility Service Installation (Main St/Jefferson St) Curb and Gutter installation (Main ...