DIGGIN' DOWNTOWN UPDATE - 5/12

Last Updated 5/12/2025Posted in DIGGIN' DOWNTOWN

Date: May 9, 2025

Recent Weeks:

Storm Sewer Installation

Subgrade Preparation

Next Week:

Phase 1A Washington Street

Monday 5/12 to Friday 5/16  – Contractor to continue storm sewer installation on west side of Fillmore Street and subgrade preparation on east side of Washington Street. Contractor will begin installing subbase on east side of Washington Street toward the end of the week.

Phase 1B Main Street

Monday 5/12 Main Street will be closed to traffic as the contractor begins pavement removals.

Looking Ahead:

Washington Street will remain closed as storm sewer installation and paving preparation continues through the following weeks.


DIGGIN' DOWNTOWN UPDATE - 6/20Date: June 20, 2025 Recent Weeks: Subdrain Installation (Washington St) Concrete Paving Operations (Washington St) Permeable Paver Insta...
Ribbon Cutting Celebrates Plant Therapy Co.'s Grand Open... On June 20 , Osceola Chamber-Main Street and community members gathered to celebrate the grand opening of Plant Therapy Co. at 203 S. Ma...
DIGGIN DOWNTOWN UPDATE - 6/13Date: June 13, 2025 Recent Weeks: Subdrain Installation (Washington St) Concrete Paving Operations (Washington St) Storm Sewer Installat...
DIGGIN' DOWNTOWN UPDATE - 6/6Date: June 6, 2025 Recent Weeks: Subdrain Installation (Washington St) Concrete Paving Operations (Washington St) Storm Sewer installati...