DIGGIN' DOWNTOWN UPDATE - 5/16

Last Updated 7/21/2025Posted in DIGGIN' DOWNTOWN

Date: May 16, 2025

Recent Weeks:

Storm Sewer Installation (Washington St)

Concrete Paving Operations (Washington St)

Pavement Removals (Main Street)

Next Week:

Phase 1A Washington Street

Saturday 5/17 – Contractor to be on site to continue paving operations on Washington Street.

Monday 5/19 to Friday 5/23 – Contractor to continue paving operations, begin sidewalk installation, and begin subdrain installation on east side of Washington Street. Contractor to begin subdrain installation and subgrade preparation on west side of Washington Street.

Phase 1B Main Street

Monday 5/19 to Friday 5/23 – Contractor to complete pavement removals on Main Street.

Looking Ahead:

Washington Street will remain closed as paving operations continue throughout the following weeks. Main Street will remain closed for utility installation.

Diggin Downtown Update - 10/17Date: October 17, 2025 Recent Weeks: Underground Utility Service installation (Main St/Jefferson St) Curb and Gutter installation (Main ...
Halloween Happenings: Frights, Fun, and Festivities Await! Spooky season is creeping in… and Osceola is brewing up a fang-tastic lineup of Halloween fun for all ages! From family trick-or-treatin...
Diggin Downtown Update - 10/10Date: October 10, 2025 Recent Weeks: Underground Utility Service Installation (East Jefferson St) Lighting System Installation (Washingt...
A New Chapter Begins at The Velvet Nook & RoastDowntown Osceola is turning the page on something truly special! On Tuesday, September 30, we gathered to celebrate the ribbon cutting a...