DIGGIN' DOWNTOWN UPDATE - 5/23

Last Updated 7/21/2025Posted in DIGGIN' DOWNTOWN

Date: May 23, 2025


Recent Weeks:

Subdrain Installation (Washington St)

Concrete Paving Operations (Washington St)

Pavement Removals (Main Street)

Next Week:

Phase 1A Washington Street

Monday 5/26 (Memorial Day) – No work due to holiday.

Tuesday 5/27 to Friday 5/30 – Contractor to continue subdrain installation and prepare for paving at intersection of Fillmore and Washington Street.

Phase 1B Main Street

Monday 5/26 (Memorial Day) – No work due to holiday.

Tuesday 5/27 to Friday 5/30 – Contractor to begin storm sewer utility work.

Looking Ahead: Washington Street will remain closed as paving operations continue throughout the following weeks. Main Street will remain closed for utility installation.

Osceola175 - Honoring Community ServiceDid you know one of Osceola’s most meaningful traditions began more than 75 years ago? In 1950, the Community Service Award was establis...
Nominations Are Now Being Accepted for the Annual Commun... This prestigious award was initiated in 1950 by Osceola Rotary Chapter and Osceola Chamber - Main Street to recognize an individual with...
DIGGIN DOWNTOWN UPDATE - 1/30/26Date: January 30, 2026 Recent Weeks: Sanitary Sewer Installation (Jefferson St) Next Week: Phase 2A Jefferson Street. Monday 2/2 to Frid...
2025 By the Numbers: Ribbon CuttingsAs we look back on 2025, one thing is clear: it was a year of growth, momentum, and new beginnings for Osceola. Throughout the year, ent...