DIGGIN' DOWNTOWN UPDATE - 5/30

Last Updated 6/2/2025Posted in DIGGIN' DOWNTOWN

Date: May 30, 2025 

Recent Weeks:
Subdrain Installation (Washington St)
Concrete Paving Operations (Washington St)

Next Week:
Phase 1A Washington Street Monday 6/2 to Friday 6/6 – Contractor to continue subdrain installation and concrete paving along Washington Street.

Phase 1B Main Street Monday 6/2 to Friday 6/6– Contractor to install storm sewer utility.

Looking Ahead:
Washington Street will remain closed as paving operations continue throughout the following weeks. Main Street will remain closed for utility installation.
DIGGIN' DOWNTOWN UPDATE - 6/6Date: June 6, 2025 Recent Weeks: Subdrain Installation (Washington St) Concrete Paving Operations (Washington St) Storm Sewer installati...
DIGGIN' DOWNTOWN UPDATE - 5/30Date: May 30, 2025 Recent Weeks: Subdrain Installation (Washington St) Concrete Paving Operations (Washington St) Next Week: Phase 1A Wa...
DIGGIN' DOWNTOWN UPDATE - 5/23Date: May 23, 2025 Recent Weeks: Subdrain Installation (Washington St) Concrete Paving Operations (Washington St) Pavement Removals (Mai...
Welcome to Osceola, Droppett! | Ribbon Cutting + Coffee... On May 15,we had the pleasure of officially welcoming Droppett to Osceola with a celebratory Ribbon Cutting and Coffee Connections event...