DIGGIN DOWNTOWN UPDATE - 6/13
Date: June 13, 2025
Recent Weeks:
Subdrain Installation (Washington St)
Concrete Paving Operations (Washington St)
Storm Sewer Installation (Main Street)
Next Week:
Phase 1A Washington Street
Monday 6/16 to Friday 6/20 – Final touches on PCC pavement work on Washington Street West of the Fillmore Intersection
Contractor to continue driveway, sidewalk, curb and gutter for Washington Street East of Fillmore Intersection
Subbase and subdrain operations in preparation for permeable pavers
Phase 1B Main Street
Monday 6/16 to Friday 6/20– Contractor to continue storm sewer utility installation and begin water main installation.
Looking Ahead:
Washington Street will remain closed as paving operations and permeable paver preparation continue throughout the following weeks. Main Street will remain closed for utility installation.
Tentative Schedule - The week of July 7 to begin installation of sanitary and water service lines to the buildings along Main Street (this is when sidewalk and water interruptions would occur).