DIGGIN DOWNTOWN UPDATE - 6/13

Last Updated 6/16/2025Posted in DIGGIN' DOWNTOWN

Date: June 13, 2025 
Recent Weeks:
Subdrain Installation (Washington St)
Concrete Paving Operations (Washington St)
Storm Sewer Installation (Main Street)

Next Week:
Phase 1A Washington Street
Monday 6/16 to Friday 6/20 – Final touches on PCC pavement work on Washington Street West of the Fillmore Intersection
Contractor to continue driveway, sidewalk, curb and gutter for Washington Street East of Fillmore Intersection
Subbase and subdrain operations in preparation for permeable pavers

Phase 1B Main Street
Monday 6/16 to Friday 6/20– Contractor to continue storm sewer utility installation and begin water main installation.

Looking Ahead:
Washington Street will remain closed as paving operations and permeable paver preparation continue throughout the following weeks. Main Street will remain closed for utility installation.
Tentative Schedule - The week of July 7 to begin installation of sanitary and water service lines to the buildings along Main Street (this is when sidewalk and water interruptions would occur).
DIGGIN DOWNTOWN UPDATE - 6/13Date: June 13, 2025 Recent Weeks: Subdrain Installation (Washington St) Concrete Paving Operations (Washington St) Storm Sewer Installat...
DIGGIN' DOWNTOWN UPDATE - 6/6Date: June 6, 2025 Recent Weeks: Subdrain Installation (Washington St) Concrete Paving Operations (Washington St) Storm Sewer installati...
DIGGIN' DOWNTOWN UPDATE - 5/30Date: May 30, 2025 Recent Weeks: Subdrain Installation (Washington St) Concrete Paving Operations (Washington St) Next Week: Phase 1A Wa...
DIGGIN' DOWNTOWN UPDATE - 5/23Date: May 23, 2025 Recent Weeks: Subdrain Installation (Washington St) Concrete Paving Operations (Washington St) Pavement Removals (Mai...