DIGGIN' DOWNTOWN UPDATE - 6/20

Last Updated 9/26/2025Posted in DIGGIN' DOWNTOWN

Date: June 20, 2025

Recent Weeks:

Subdrain Installation (Washington St)

Concrete Paving Operations (Washington St)

Permeable Paver Installation (Washington St)

Storm Sewer Installation (Main Street)

Next Week:

Phase 1A Washington Street

Monday 6/23 to Friday 6/27 – Contractor to continue permeable paver installation along the north side of Washington Street. Contractor to continue subdrain and PCC curb and gutter along the south side of Washington street.

Contractor will work on pavement removals on Washington Street east of Main Street. This section of Washington Street will be closed to traffic. Once removals have been completed the contractor will begin storm sewer installation in this area.

Phase 1B Main Street

Monday 6/23 to Friday 6/27– Utility installation will continue at the intersection of Main Street and Washington Street.

Looking Ahead:

Washington Street will remain closed as paving and utility operations continue throughout the following weeks. Main Street will remain closed for utility installation.


Shop Local This Holiday Season: Osceola Has Something fo... The holiday season is officially here, and as we inch closer to Shop Small Saturday on November 29 , our local businesses are buzzing wi...
DIGGIN DOWNTOWN UPDATE - 11/7Date: November 7, 2025 Recent Weeks: Underground Utility Service Installation (Jefferson St) Permeable Paver installation (Main St) Side...
DIGGIN DOWNTOWN UPDATE - 10/31Date: October 31, 2025 Recent Weeks: Underground Utility Service Installation (Main St/E Jefferson St) Permeable Paver Installation (Mai...
DIGGIN DOWNTOWN UPDATE - 10/24Date: October 24, 2025 Recent Weeks: Underground Utility Service Installation (Main St/Jefferson St) Curb and Gutter installation (Main ...