DIGGIN' DOWNTOWN UPDATE - 6/27
Date: June 27, 2025
Recent Weeks:
-Concrete Paving Operations (Washington St)
-Permeable Paver Installation (Washington St)
-Storm Sewer installation (Main Street)
Next Week:
Phase 1A Washington Street
Monday 6/30 to Thursday 7/3 – Contractor to continue permeable paver and curb and gutter installation along Washington Street. Contractor to backfill behind the curb on the west end of Washington Street.
Phase 1B Main Street
Monday 6/30 to Thursday 7/3 – Utility installation will continue along Main Street and the intersection of Main Street and Washington Street.
*There will be no work completed on Friday July 4th.
Looking Ahead:
Washington Street will remain closed as paving and utility operations continue throughout the following weeks. Main Street will remain closed for utility installation.
The tentative start date for water service hookups to Main Street buildings, originally set for the week of July 7, is now expected to take place toward the end of July.