DIGGIN DOWNTOWN UPDATE - 8/22

Last Updated 8/29/2025Posted in DIGGIN' DOWNTOWN

Date: August 22, 2025

 Recent Weeks:

Pavement Removals (Jefferson & Main Intersection)

Underground Utility Installation (Main St)

Subgrade Preparation (East Washington St)

Washington Street West of the Main Street Intersection has opened                                                      

 Next Week:

Phase 1A Washington Street

Monday 8/25 to Friday 8/29 – Contractor to complete subbase and subdrain installation along East Washington Street.

Phase 1B Main Street

Monday 8/25 to Friday 8/29 – Contractor to continue sanitary service replacements and begin water service replacements along Main Street.

*Please note – Sections of sidewalk along Main Street will be inaccessible while water/sanitary service installation is underway.

Looking Ahead:

East Washington Street will remain closed as paving preparation and installation continues throughout the following weeks. Main Street and the intersection of Main Street and Jefferson Street will remain closed for utility installation.

Osceola175 - Honoring Community ServiceDid you know one of Osceola’s most meaningful traditions began more than 75 years ago? In 1950, the Community Service Award was establis...
Nominations Are Now Being Accepted for the Annual Commun... This prestigious award was initiated in 1950 by Osceola Rotary Chapter and Osceola Chamber - Main Street to recognize an individual with...
DIGGIN DOWNTOWN UPDATE - 1/30/26Date: January 30, 2026 Recent Weeks: Sanitary Sewer Installation (Jefferson St) Next Week: Phase 2A Jefferson Street. Monday 2/2 to Frid...
2025 By the Numbers: Ribbon CuttingsAs we look back on 2025, one thing is clear: it was a year of growth, momentum, and new beginnings for Osceola. Throughout the year, ent...