DIGGIN DOWNTOWN UPDATE - 8/29

Last Updated 8/29/2025Posted in DIGGIN' DOWNTOWN

Date: August 29, 2025


Recent Weeks:

Underground Utility Service Installation (Main St)

Paving Operations (East Washington St)

Fillmore and Washington Intersection has opened

 

Next Week:

(No work to be completed on Monday due to holiday)

Phase 1A Washington Street

Tuesday 9/2 to Friday 9/5 – Contractor to continue paving operations on East Washington Street.

Phase 1B Main Street

Tuesday 9/2 to Friday 9/5 – Contractor to continue water and sanitary service replacement along Main Street.

*Please note – Sections of sidewalk along Main Street will be inaccessible while water/sanitary service installation is underway.


Looking Ahead:

East Washington Street will remain closed as paving preparation and installation continues throughout the following weeks. Main Street and the intersection of Main Street and Jefferson Street will remain closed for utility installation.

Osceola175 - Honoring Community ServiceDid you know one of Osceola’s most meaningful traditions began more than 75 years ago? In 1950, the Community Service Award was establis...
Nominations Are Now Being Accepted for the Annual Commun... This prestigious award was initiated in 1950 by Osceola Rotary Chapter and Osceola Chamber - Main Street to recognize an individual with...
DIGGIN DOWNTOWN UPDATE - 1/30/26Date: January 30, 2026 Recent Weeks: Sanitary Sewer Installation (Jefferson St) Next Week: Phase 2A Jefferson Street. Monday 2/2 to Frid...
2025 By the Numbers: Ribbon CuttingsAs we look back on 2025, one thing is clear: it was a year of growth, momentum, and new beginnings for Osceola. Throughout the year, ent...