DIGGIN DOWNTOWN UPDATE - 8/29
Date: August 29, 2025
Recent Weeks:
Underground Utility Service Installation (Main St)
Paving Operations (East Washington St)
Fillmore and Washington Intersection has opened
Next Week:
(No work to be completed on Monday due to holiday)
Phase 1A Washington Street
Tuesday 9/2 to Friday 9/5 – Contractor to continue paving operations on East Washington Street.
Phase 1B Main Street
Tuesday 9/2 to Friday 9/5 – Contractor to continue water and sanitary service replacement along Main Street.
*Please note – Sections of sidewalk along Main Street will be inaccessible while water/sanitary service installation is underway.
Looking Ahead:
East Washington Street will remain closed as paving preparation and installation continues throughout the following weeks. Main Street and the intersection of Main Street and Jefferson Street will remain closed for utility installation.