DIGGIN DOWNTOWN UPDATE - 8/29

Last Updated 8/29/2025Posted in DIGGIN' DOWNTOWN

Date: August 29, 2025


Recent Weeks:

Underground Utility Service Installation (Main St)

Paving Operations (East Washington St)

Fillmore and Washington Intersection has opened

 

Next Week:

(No work to be completed on Monday due to holiday)

Phase 1A Washington Street

Tuesday 9/2 to Friday 9/5 – Contractor to continue paving operations on East Washington Street.

Phase 1B Main Street

Tuesday 9/2 to Friday 9/5 – Contractor to continue water and sanitary service replacement along Main Street.

*Please note – Sections of sidewalk along Main Street will be inaccessible while water/sanitary service installation is underway.


Looking Ahead:

East Washington Street will remain closed as paving preparation and installation continues throughout the following weeks. Main Street and the intersection of Main Street and Jefferson Street will remain closed for utility installation.

DIGGIN DOWNTOWN UPDATE - 3/13Date: March 13, 2026 Recent Weeks: Sanitary Sewer Service Installation (Fillmore St) Storm Sewer Installation (Fillmore St) Curb and Gut...
Celebrating Community at the Greater Osceola Partnership... On Friday, March 6, the Greater Osceola Partnership Annual Dinner was held, in partnership with the Osceola Chamber Main Street and Clar...
DIGGIN DOWNTOWN 3/6Date: March 6, 2026 Recent Weeks: Water Service Installation (Fillmore St) Sanitary Sewer Service Installation (Fillmore St) Paving Prep...
DIGGIN' DOWNTOWN UPDATE - 2/27Date: February 27, 2026 Recent Weeks: Water Service Installation (Fillmore St) Paving Preparation and Installation (Jefferson St) Next W...