Diggin' Downtown Update - 10/3
Date: October 3, 2025
Recent Weeks:
Underground Utility Service Installation (Main St/Jefferson St)
Lighting System Installation (Washington St/Main St)
Paving Operations (Main St)
Next Week:
Phase 1A Washington Street/Main Street
Monday 10/6 to Friday 10/10
Contractor to install sidewalk ramps at intersection of Washington and Main Street. Contractor will then begin subdrain and curb and gutter installation along Main Street.
Phase 1B Jefferson Street
Monday 10/6 to Friday 10/10
Contractor to complete storm sewer and sanitary sewer installation along East Jefferson Street.
Looking Ahead:
Main Street will remain closed from Washington intersection through Jefferson intersection for paving operations. East Jefferson to remain closed for utility installation.