Diggin' Downtown Update - 10/3

Last Updated 10/20/2025Posted in DIGGIN' DOWNTOWN

Date: October 3, 2025

Recent Weeks:

Underground Utility Service Installation (Main St/Jefferson St)

Lighting System Installation (Washington St/Main St)

Paving Operations (Main St)


Next Week:

Phase 1A Washington Street/Main Street

Monday 10/6 to Friday 10/10 

Contractor to install sidewalk ramps at intersection of Washington and Main Street. Contractor will then begin subdrain and curb and gutter installation along Main Street.

Phase 1B Jefferson Street

Monday 10/6 to Friday 10/10 

Contractor to complete storm sewer and sanitary sewer installation along East Jefferson Street.

Looking Ahead:

Main Street will remain closed from Washington intersection through Jefferson intersection for paving operations. East Jefferson to remain closed for utility installation.

2025 By the Numbers: Ribbon CuttingsAs we look back on 2025, one thing is clear: it was a year of growth, momentum, and new beginnings for Osceola. Throughout the year, ent...
2025 By the Numbers: Placemaking in OsceolaIn 2025, placemaking in Osceola focused on creating color, ambiance, and joy throughout downtown and across the community. Through a ser...
Osceola175 - Glimpses of the Past: Osceola Tourist Camp:... In the early days of automobile travel, roadside tourist camps were essential stops for travelers exploring America’s growing highway sy...
Osceola 175 – Glimpses Of The Past: Fire & Fortitude On ... A Downtown Forged by Fire Between 1874 and today, 45 major fires swept through downtown Osceola, repeatedly reshaping the square. Each b...