Diggin Downtown Update - 10/10
Date: October 10, 2025
Recent Weeks:
Underground Utility Service Installation (East Jefferson St)
Lighting System Installation (Washington St/Main St)
Paving Operations (Main St)
Next Week:
Phase 1B Main Street
Monday 10/13 to Friday 10/17 - Contractor to install curb and gutter, subdrain, and sidewalk along Main Street
Phase 1B Main Street/Jefferson Street
Monday 10/13 to Friday 10/17 – Contractor to complete sanitary sewer and service installation.
Looking Ahead:
Main Street will remain closed from Washington intersection through Jefferson intersection for paving operations. East Jefferson to remain closed for utility installation.