Diggin Downtown Update - 10/10

Last Updated 10/20/2025Posted in DIGGIN' DOWNTOWN

Date: October 10, 2025

Recent Weeks:
Underground Utility Service Installation (East Jefferson St)
Lighting System Installation (Washington St/Main St)
Paving Operations (Main St)
Next Week:
Phase 1B Main Street
Monday 10/13 to Friday 10/17 - Contractor to install curb and gutter, subdrain, and sidewalk along Main Street
Phase 1B Main Street/Jefferson Street
Monday 10/13 to Friday 10/17 – Contractor to complete sanitary sewer and service installation.
Looking Ahead:
Main Street will remain closed from Washington intersection through Jefferson intersection for paving operations. East Jefferson to remain closed for utility installation.
2025 By the Numbers: Ribbon CuttingsAs we look back on 2025, one thing is clear: it was a year of growth, momentum, and new beginnings for Osceola. Throughout the year, ent...
2025 By the Numbers: Placemaking in OsceolaIn 2025, placemaking in Osceola focused on creating color, ambiance, and joy throughout downtown and across the community. Through a ser...
Osceola175 - Glimpses of the Past: Osceola Tourist Camp:... In the early days of automobile travel, roadside tourist camps were essential stops for travelers exploring America’s growing highway sy...
Osceola 175 – Glimpses Of The Past: Fire & Fortitude On ... A Downtown Forged by Fire Between 1874 and today, 45 major fires swept through downtown Osceola, repeatedly reshaping the square. Each b...