DIGGIN DOWNTOWN UPDATE - 12/5

Last Updated 12/15/2025Posted in DIGGIN' DOWNTOWN

Date: December 5, 2025  

Recent Weeks:

Underground Utility Service Installation (Jefferson St)

Paving Operations (Main St/Jefferson St)

Next Week:

Phase 1B Main Street/East Jefferson Street Intersection.

Monday 12/8 to Friday 12/12– Contractor to continue sidewalk paving operations as weather allows. Phase 2A Jefferson Street.

Monday 12/8 to Friday 12/12– Contractor to continue sanitary sewer installation.

Looking Ahead:

Main Street and the intersection of Main Street and Jefferson Street will remain closed for paving operations. Jefferson Street between Main Street and Fillmore Street will remain closed for utility installation.

DIGGIN DOWNTOWN UPDATE - 12/12/25Date: December 12, 2025 Recent Weeks: Underground Utility Service Installation (W. Jefferson St) Paving Operations (Main St/East Jeffers...
Christmas in the Park Brings Holiday Magic to Downtown O... Downtown Osceola came to life on Saturday, December 6, as families, friends, and visitors gathered to celebrate one of our favorite comm...
DIGGIN DOWNTOWN UPDATE - 12/5Date: December 5, 2025 Recent Weeks: Underground Utility Service Installation (Jefferson St) Paving Operations (Main St/Jefferson St) Ne...
Diggin' Downtown Update 11/26Date: November 26, 2025 Recent Weeks: Underground Utility Service Installation (West Jefferson St) Subgrade Compaction, Subbase, Subdrai...