DIGGIN DOWNTOWN UPDATE - 12/5
Date: December 5, 2025
Recent Weeks:
Underground Utility Service Installation (Jefferson St)
Paving Operations (Main St/Jefferson St)
Next Week:
Phase 1B Main Street/East Jefferson Street Intersection.
Monday 12/8 to Friday 12/12– Contractor to continue sidewalk paving operations as weather allows. Phase 2A Jefferson Street.
Monday 12/8 to Friday 12/12– Contractor to continue sanitary sewer installation.
Looking Ahead:
Main Street and the intersection of Main Street and Jefferson Street will remain closed for paving operations. Jefferson Street between Main Street and Fillmore Street will remain closed for utility installation.


.jpg)