Downtown Streetscape Construction Project Beginning Monday

Last Updated 12/14/2024Posted in DIGGIN' DOWNTOWN


Date: December 13, 2024

Next Week: Phase 1A Washington Street Monday

12/16 – Washington Street will be closed for construction from the Water Tower to Main Street. Main Street shall remain open to both lanes of traffic. Fillmore Street intersection will be closed at Washington Street. The contractor will set up traffic control detours & construction fencing. Washington Street north sidewalk will be open for pedestrian traffic. Contractor anticipates starting milling of the asphalt within Phase 1A construction area. Tuesday-Wednesday 12/17-12/18 – Contractor will continue with partial existing pavement removal consisting of milling the top asphalt surface. Thursday-Friday 12/19-12/20 – Contractor anticipates starting installation of new water main utility improvements on Washington Street.

Looking Ahead:

Water main construction will continue through the following weeks.

Contact Information:

              Ty Wheeler                                                              Ashleigh Eckels

              City Administrator                                               Main Street Director & Business Liaison

              641-342-2377                                                        641-342-4200

              [email protected]                                    [email protected]


Read Full Update Here.


Main Street Closure and Washinton Street Progress: What’... Significant progress is underway in downtown as infrastructure improvements continue to move forward along Washington Street. Crews have...
DIGGIN' DOWNTOWN UPDATE - 4/25Date: April 25, 2025 Recent Weeks: Storm Sewer Installation Next Week: Phase 1A Washington Street Monday 4/28 to Friday 5/2 – Contractor...
DIGGIN' DOWNTOWN UPDATE - 4/18Date: April 18, 2025 Recent Weeks: Storm Sewer Installation Sidewalk Installation ADA Accessible Ramps Poured Next Week: Phase 1A Washin...
DIGGIN' DOWNTOWN UPDATE - 4/11Date: April 11, 2025 This Past Week: Storm Sewer Installation Sidewalk Installation Next Week: Phase 1A Washington Street Monday 4/14 to...