Downtown Streetscape Construction Project Beginning Monday

Last Updated 12/14/2024Posted in DIGGIN' DOWNTOWN


Date: December 13, 2024

Next Week: Phase 1A Washington Street Monday

12/16 – Washington Street will be closed for construction from the Water Tower to Main Street. Main Street shall remain open to both lanes of traffic. Fillmore Street intersection will be closed at Washington Street. The contractor will set up traffic control detours & construction fencing. Washington Street north sidewalk will be open for pedestrian traffic. Contractor anticipates starting milling of the asphalt within Phase 1A construction area. Tuesday-Wednesday 12/17-12/18 – Contractor will continue with partial existing pavement removal consisting of milling the top asphalt surface. Thursday-Friday 12/19-12/20 – Contractor anticipates starting installation of new water main utility improvements on Washington Street.

Looking Ahead:

Water main construction will continue through the following weeks.

Contact Information:

              Ty Wheeler                                                              Ashleigh Eckels

              City Administrator                                               Main Street Director & Business Liaison

              641-342-2377                                                        641-342-4200

              [email protected]                                    [email protected]


Read Full Update Here.


Osceola Chamber Main Street Lights Up Downtown with New ... Osceola Chamber Main Street has taken another bold step in transforming the heart of downtown into a vibrant, welcoming destination. The...
DIGGIN DOWNTOWN UPDATE - 8/8Date: August 8, 2025 Recent Weeks: Concrete Paving Operations (Washington & Main St) Underground Utility Installation (Washington Street...
DIGGIN DOWNTOWN UPDATE - 7/25Date: July 25, 2025 Recent Weeks: Concrete Paving Operations (Washington St) Permeable Paver Installation (Washington St) Storm Sewer in...
DIGGIN' DOWNTOWN CONSTRUCITON SCHEDULE OVERVIEWRemainder of July East Washington utility work Washington street pavers and concrete operations Subgrade prep on Main/Washington Interse...