Recent Weeks:
Underground Utility Service Installation (East Jefferson St)
Lighting System Installation (Washington St/Main St)
Paving Operations (Main St)
Next Week:
Phase 1B Main Street
Monday 10/13 to Friday 10/17 - Contractor to install curb and gutter, subdrain, and sidewalk along Main Street
Phase 1B Main Street/Jefferson Street
Monday 10/13 to Friday 10/17 – Contractor to complete sanitary sewer and service installation.
Looking Ahead:
Main Street will remain closed from Washington intersection through Jefferson intersection for paving operations. East Jefferson to remain closed for utility installation.
DIGGIN DOWNTOWN UPDATE - 6/19Date: June 19, 2026 Recent Weeks: The square is now all open to traffic! Sidewalk Installation (Fillmore St) Light Pole Installation (Fi...
Swing By the Pocket ParkSometimes the best projects take time. What began as a simple idea nearly five years ago has grown into one of downtown Osceola's newest...
DIGGIN DOWNTOWN UPDATE - 6/12Date: June 12, 2026 Recent Weeks: Sidewalk Installation (Fillmore St) Road Paving (Fillmore St) Light Pole Installation (Fillmore St) Se...
DIGGIN DOWNTOWN UPDATE - 6/5Date: June 5, 2026 Recent Weeks: Permeable Paver Installation (Fillmore St) Sidewalk Installation (Fillmore St) Road Paving (Fillmore St...