DIGGIN DOWNTOWN UPDATE - 6/19

Last Updated 10/13/2026 • Posted in DIGGIN' DOWNTOWN

Date: June 19, 2026

Recent Weeks:

The square is now all open to traffic!

Sidewalk Installation (Fillmore St)

Light Pole Installation (Fillmore St)

Seeding/Restoration (Fillmore St)

Joint Filling & Pavement Striping (Fillmore St)

Next Week:

Phase 2B Fillmore Street.

Monday 6/22 to Friday 6/26:

·         Continue installation of permeable pavers in the Fillmore Street Alley

·         Continue site cleanup and restoration

Looking Ahead:

The alley at mid-block of Fillmore Street will remain closed for permeable paver installation. The Jefferson Street mid-block alley will begin after the Fillmore Street alley is completed.

Downtown Spooktacular Brings Halloween Fun to the Square!What a SPOOKTACULAR night in Downtown Osceola! Our annual Downtown Spooktacular on Friday, October 23, brought families, friends, and pl...
Swing By the Pocket ParkSometimes the best projects take time. What began as a simple idea nearly five years ago has grown into one of downtown Osceola's newest...
DIGGIN DOWNTOWN UPDATE - 6/12Date: June 12, 2026 Recent Weeks: Sidewalk Installation (Fillmore St) Road Paving (Fillmore St) Light Pole Installation (Fillmore St) Se...
DIGGIN DOWNTOWN UPDATE - 6/5Date: June 5, 2026 Recent Weeks: Permeable Paver Installation (Fillmore St) Sidewalk Installation (Fillmore St) Road Paving (Fillmore St...