Diggin Downtown Update - 10/17

Last Updated 10/20/2025Posted in DIGGIN' DOWNTOWN

Date: October 17, 2025

 Recent Weeks:

Underground Utility Service installation (Main St/Jefferson St)

Curb and Gutter installation (Main St)

Subdrain installation (Main St)

Light pole Installation (Washington Street)

Next Week:

Phase 1B Main Street

Monday 10/20 to Friday 10/24 – Contractor to complete sidewalk installation on Main Street and begin permeable paver installation.

Phase 1B Main Street/East Jefferson Street.

Monday 10/20 to Friday 10/24 – Contractor to complete sanitary sewer, storm sewer, and water service installation along East Jefferson.

Phase 2A Jefferson Street

Wednesday 10/22 to Friday 10/24 – Pavement removals to begin on West Jefferson to prepare for utility installation the following week.  East side of Fillmore to close for staging of material/equipment.

Looking Ahead:

Main Street will remain closed from Washington intersection through Jefferson intersection for paving operations. East Jefferson to remain closed for utility installation. West Jefferson and East Side of Fillmore to be closed for next phase of construction.

Diggin' Downtown Update 11/26Date: November 26, 2025 Recent Weeks: Underground Utility Service Installation (West Jefferson St) Subgrade Compaction, Subbase, Subdrai...
Diggin Downtown Update 11/21Date: November 21, 2025 Recent Weeks: Underground Utility Service Installation (Jefferson St) Subgrade Compaction, Subbase, Subdrain Ins...
Shop Local This Holiday Season: Osceola Has Something fo... The holiday season is officially here, and as we inch closer to Shop Small Saturday on November 29 , our local businesses are buzzing wi...
Diggin Downtown Update - 11/14Date: November 14, 2025 Recent Weeks: Underground Utility Service Installation (W Jefferson St) Subgrade Compaction, Subbase and Subdrai...