Diggin Downtown Update - 10/17

Last Updated 10/20/2025Posted in DIGGIN' DOWNTOWN

Date: October 17, 2025

 Recent Weeks:

Underground Utility Service installation (Main St/Jefferson St)

Curb and Gutter installation (Main St)

Subdrain installation (Main St)

Light pole Installation (Washington Street)

Next Week:

Phase 1B Main Street

Monday 10/20 to Friday 10/24 – Contractor to complete sidewalk installation on Main Street and begin permeable paver installation.

Phase 1B Main Street/East Jefferson Street.

Monday 10/20 to Friday 10/24 – Contractor to complete sanitary sewer, storm sewer, and water service installation along East Jefferson.

Phase 2A Jefferson Street

Wednesday 10/22 to Friday 10/24 – Pavement removals to begin on West Jefferson to prepare for utility installation the following week.  East side of Fillmore to close for staging of material/equipment.

Looking Ahead:

Main Street will remain closed from Washington intersection through Jefferson intersection for paving operations. East Jefferson to remain closed for utility installation. West Jefferson and East Side of Fillmore to be closed for next phase of construction.

DIGGIN DOWNTOWN UPDATE - 4/24Date: April 24, 2026 Recent Weeks: Sanitary Sewer/Water Main Installation (Fillmore St) Paving Preparation (Fillmore St) Next Week: Phas...
DIGGIN DOWNTOWN UPDATE - 4/17Date: April 17, 2026 Recent Weeks: Storm Sewer/Water Main Installation (Fillmore St) Sidewalk Installation (Fillmore St) Next Week: Phas...
DIGGIN DOWNTOWN UPDATE - 4/3Date: April 3, 2026 Recent Weeks: Storm Sewer Installation (Fillmore St) Pavement Removal (Fillmore St) Permeable Paver Installation (Je...
DIGGIN DOWNTOWN UPDATE - 3/30Date: March 27, 2026 Recent Weeks: Storm Sewer Installation (Fillmore St) Curb and Gutter Installation (Jefferson St) Permeable Paver In...