DIGGIN DOWNTOWN UPDATE - 12/12/25

Last Updated 12/15/2025Posted in DIGGIN' DOWNTOWN

Date: December 12, 2025 
Recent Weeks:
Underground Utility Service Installation (W. Jefferson St)
Paving Operations (Main St/East Jefferson St)
Next Week:
Phase 1B Main Street/East Jefferson Street Intersection.
Monday 12/15 to Friday 12/19– Contractor to continue sidewalk paving operations as weather allows.

Phase 2A Jefferson Street.
Monday 12/15 to Friday 12/19– Contractor to continue sanitary sewer installation. Sidewalk interruptions while building sanitary sewer lines are replaced.

Looking Ahead:
Main Street and the intersection of Main Street and Jefferson Street will remain closed for paving operations. Jefferson Street between Main Street and Fillmore Street will remain closed for utility installation. Fillmore Street is tentatively scheduled to fully close January 5 (weather dependent).
DIGGIN DOWNTOWN UPDATE - 4/24Date: April 24, 2026 Recent Weeks: Sanitary Sewer/Water Main Installation (Fillmore St) Paving Preparation (Fillmore St) Next Week: Phas...
DIGGIN DOWNTOWN UPDATE - 4/17Date: April 17, 2026 Recent Weeks: Storm Sewer/Water Main Installation (Fillmore St) Sidewalk Installation (Fillmore St) Next Week: Phas...
DIGGIN DOWNTOWN UPDATE - 4/3Date: April 3, 2026 Recent Weeks: Storm Sewer Installation (Fillmore St) Pavement Removal (Fillmore St) Permeable Paver Installation (Je...
DIGGIN DOWNTOWN UPDATE - 3/30Date: March 27, 2026 Recent Weeks: Storm Sewer Installation (Fillmore St) Curb and Gutter Installation (Jefferson St) Permeable Paver In...