Recent Weeks:
Underground Utility Service Installation (Jefferson St)
Sidewalk Installation (Main St/East Jefferson St)
Main Street & East Jefferson is Now Open

Next Week: Phase 2A Jefferson Street.
Monday 12/22 to Wednesday 12/24– Contractor to continue sanitary sewer installation and begin sidewalk installation west of Main/Jefferson intersection.
Thursday 12/25 – No work anticipated on site.
Friday 12/26 – Contractor may be on site to continue sidewalk installation.

Looking Ahead:
West Jefferson Street between Main Street and Fillmore Street will remain closed for utility installation. All of Fillmore Street is anticipated to close in January (weather dependent).

DIGGIN DOWNTOWN UPDATE - 3/13Date: March 13, 2026 Recent Weeks: Sanitary Sewer Service Installation (Fillmore St) Storm Sewer Installation (Fillmore St) Curb and Gut...
Celebrating Community at the Greater Osceola Partnership... On Friday, March 6, the Greater Osceola Partnership Annual Dinner was held, in partnership with the Osceola Chamber Main Street and Clar...
DIGGIN DOWNTOWN 3/6Date: March 6, 2026 Recent Weeks: Water Service Installation (Fillmore St) Sanitary Sewer Service Installation (Fillmore St) Paving Prep...
DIGGIN' DOWNTOWN UPDATE - 2/27Date: February 27, 2026 Recent Weeks: Water Service Installation (Fillmore St) Paving Preparation and Installation (Jefferson St) Next W...