DIGGIN DOWNTOWN UPDATE - 6/19
Date: June 19, 2026
Recent Weeks:
The square is now all open to traffic!
Sidewalk Installation (Fillmore St)
Light Pole Installation (Fillmore St)
Seeding/Restoration (Fillmore St)
Joint Filling & Pavement Striping (Fillmore St)
Next Week:
Phase 2B Fillmore Street.
Monday 6/22 to Friday 6/26:
· Continue installation of permeable pavers in the Fillmore Street Alley
· Continue site cleanup and restoration
Looking Ahead:
The alley at mid-block of Fillmore Street will remain closed for permeable paver installation. The Jefferson Street mid-block alley will begin after the Fillmore Street alley is completed.