DIGGIN DOWNTOWN UPDATE - 6/19

Last Updated 6/22/2026Posted in DIGGIN' DOWNTOWN

Date: June 19, 2026

Recent Weeks:

The square is now all open to traffic!

Sidewalk Installation (Fillmore St)

Light Pole Installation (Fillmore St)

Seeding/Restoration (Fillmore St)

Joint Filling & Pavement Striping (Fillmore St)

Next Week:

Phase 2B Fillmore Street.

Monday 6/22 to Friday 6/26:

·         Continue installation of permeable pavers in the Fillmore Street Alley

·         Continue site cleanup and restoration

Looking Ahead:

The alley at mid-block of Fillmore Street will remain closed for permeable paver installation. The Jefferson Street mid-block alley will begin after the Fillmore Street alley is completed.

Swing By the Pocket ParkSometimes the best projects take time. What began as a simple idea nearly five years ago has grown into one of downtown Osceola's newest...
DIGGIN DOWNTOWN UPDATE - 6/12Date: June 12, 2026 Recent Weeks: Sidewalk Installation (Fillmore St) Road Paving (Fillmore St) Light Pole Installation (Fillmore St) Se...
DIGGIN DOWNTOWN UPDATE - 6/5Date: June 5, 2026 Recent Weeks: Permeable Paver Installation (Fillmore St) Sidewalk Installation (Fillmore St) Road Paving (Fillmore St...
DIGGIN DOWNTOWN UPDATE - 5/29Date: May 29, 2026 Recent Weeks: Permeable Paver Installation (Fillmore St) Curb and Gutter Installation (Fillmore St) Paving Preparatio...