DIGGIN DOWNTOWN UPDATE - 6/5
Date: June 5, 2026
Recent Weeks:
Permeable Paver Installation (Fillmore St)
Sidewalk Installation (Fillmore St)
Road Paving (Fillmore St/Jefferson St)
Conduit and Light Pole Base Installation (West side Fillmore St)
Stair/Handrail installation (Jefferson St)
Seeding/Restoration (Washington/Main/Jefferson St)
Next Week:
Phase 2B Fillmore Street.
Monday 6/8 to Friday 6/12:
· Finish roadway paving on south end of Fillmore St.
· Install remaining sidewalks along west side of Fillmore St.
· Begin light pole installation
Looking Ahead:
Fillmore Street and the western section of Jefferson Street will remain closed for roadway installation.