DIGGIN' DOWNTOWN UPDATE - 4/18

Last Updated 9/26/2025Posted in DIGGIN' DOWNTOWN

Date: April 18, 2025

Recent Weeks:

Storm Sewer Installation

Sidewalk Installation

ADA Accessible Ramps Poured

Next Week:

Phase 1A Washington Street

Monday 4/21 to Friday 4/25 – Contractor to continue storm sewer installation along Washington Street.

Looking Ahead:

Washington Street will remain closed as storm sewer installation continues through the following weeks.

In the upcoming weeks Main Street will be closed for pavement removal.

Once the utility crew finishes installing the storm sewer along Washington Street, they will shift their focus to Main Street to begin installing the new water main. Meanwhile, on Washington Street TK Concrete will focus on surface improvements, including road preparation, pouring new pavement, completing the remaining sidewalks, and installing permeable pavers in the on-street parking areas.

Follow along here to see the latest progress!

Swing By the Pocket ParkSometimes the best projects take time. What began as a simple idea nearly five years ago has grown into one of downtown Osceola's newest...
DIGGIN DOWNTOWN UPDATE - 6/12Date: June 12, 2026 Recent Weeks: Sidewalk Installation (Fillmore St) Road Paving (Fillmore St) Light Pole Installation (Fillmore St) Se...
DIGGIN DOWNTOWN UPDATE - 6/5Date: June 5, 2026 Recent Weeks: Permeable Paver Installation (Fillmore St) Sidewalk Installation (Fillmore St) Road Paving (Fillmore St...
DIGGIN DOWNTOWN UPDATE - 5/29Date: May 29, 2026 Recent Weeks: Permeable Paver Installation (Fillmore St) Curb and Gutter Installation (Fillmore St) Paving Preparatio...