DIGGIN' DOWNTOWN UPDATE - 5/12

Last Updated 7/21/2025Posted in DIGGIN' DOWNTOWN

Date: May 9, 2025

Recent Weeks:

Storm Sewer Installation

Subgrade Preparation

Next Week:

Phase 1A Washington Street

Monday 5/12 to Friday 5/16  – Contractor to continue storm sewer installation on west side of Fillmore Street and subgrade preparation on east side of Washington Street. Contractor will begin installing subbase on east side of Washington Street toward the end of the week.

Phase 1B Main Street

Monday 5/12 Main Street will be closed to traffic as the contractor begins pavement removals.

Looking Ahead:

Washington Street will remain closed as storm sewer installation and paving preparation continues through the following weeks.


Swing By the Pocket ParkSometimes the best projects take time. What began as a simple idea nearly five years ago has grown into one of downtown Osceola's newest...
DIGGIN DOWNTOWN UPDATE - 6/12Date: June 12, 2026 Recent Weeks: Sidewalk Installation (Fillmore St) Road Paving (Fillmore St) Light Pole Installation (Fillmore St) Se...
DIGGIN DOWNTOWN UPDATE - 6/5Date: June 5, 2026 Recent Weeks: Permeable Paver Installation (Fillmore St) Sidewalk Installation (Fillmore St) Road Paving (Fillmore St...
DIGGIN DOWNTOWN UPDATE - 5/29Date: May 29, 2026 Recent Weeks: Permeable Paver Installation (Fillmore St) Curb and Gutter Installation (Fillmore St) Paving Preparatio...